Infrastructure register
UK data-centre tracker
What stage have UK data-centre projects reached? Compare recorded planning and construction status, published power information and the evidence behind each project. Each entry records what has actually been published — status, location, capacity where it is stated — and links back to the original source. We do not estimate figures that operators have not disclosed; unstated fields are shown as "Not published".
Explore project locations on the UK data centre map → The map also shows wider supporting infrastructure such as grid, battery and substation projects.
This is an evidence-led register of projects identified from public records. It is not claimed to be a complete census of every UK data centre.
- Data-centre projects (filtered)
- 94
- Operational / under construction
- 25 / 7
- Checked in the last 90 days
- 94
5 AI Growth Zones shown separately and excluded from these totals
Approved 37 · Proposed or planning submitted 22 · Refused 1 · Paused 2
52 of 94 hold a planning reference
Published IT load, all stages incl. operational: 4,825 MW (21 of 94 projects publish a figure)
Published grid-connection capacity: 435 MW from 4 of 94 matching projects.
13 matching projects report megawatt figures whose definition the source does not state. Those figures are shown on the project profile but excluded from every total.
A missing capacity figure means none has been published. It does not mean zero.
The capacity filter uses the largest published figure whose measurement the source defines — an IT load, a stated electrical demand, a grid-connection capacity or a campus build-out figure. Megawatt figures with no published definition are treated as unknown.
Showing 99 of 99 projects
Each project carries a Reality Score assessing the public evidence behind it (not its construction status). Supplying the build? See Real Pipeline Pro.
Pure DC LON01 B2, Brent Cross
100/100 · Strong evidencePure Data Centres Group
London (Brent Cross), London
Under constructionData centre 70 MW · definition not publishedThe second and final building at Pure DC's LON01 campus at Brent Cross, north London, adding more than 23,000 sqm and taking the campus to 90MW. Glencar is the general contractor and began piling for the west shell in September 2026. Completion of B2 is scheduled for Q2 2029.
View projectEra4 AI data centre, Erin Landfill, Chesterfield
92/100 · Strong evidenceEra4 (formerly Carbon3.ai)
Chesterfield (Duckmanton / Poolsbrook), East Midlands
OperationalData centre Capacity not publishedEra4 runs a modular AI data centre of HPE AI Mod Pods on the Erin Landfill site off Erin Road near the M1, outside Chesterfield. It is powered mainly by landfill gas generated on site, with the grid as backup. Fireworks has contracted the whole site, 5MW of liquid-cooled Nvidia B300 capacity, under a multi-year deal announced in October 2026.
View projectGreenScale Derry Campus (formerly Atlantic Hub), Foyle Port
85/100 · Strong evidenceGreenScale
Derry, Northern Ireland
ApprovedData centre 100 MW · grid-connection capacityReserved matters approval (LA11/2023/1729/RM) granted by Derry City and Strabane District Council on 9 October 2024 for one IT service and data centre building with substation compounds, generators, switchgear and transformers on land east and west of Maydown Road, Derry. The statutory planning register states no capacity. The operator, GreenScale, states that the campus has secured grid connections totalling 100 MW, which is recorded here as grid-connection capacity rather than IT load.
View projectTelehouse West Two, London Docklands campus
79/100 · LikelyTelehouse (KDDI)
London (Blackwall), London
Under constructionData centre 33 MW · definition not publishedA nine-storey, 33 MW data centre under construction at Telehouse's Docklands campus, due to open in 2028. Telehouse reports piling and ground works complete and steelwork started. Investment put at £275m. It will combine air and liquid cooling.
View projectPremier Park data centre, Park Royal
78/100 · LikelyPure DC
London, London
ApprovedData centre Capacity not publishedDemolition of an existing building at Unit F, 6 Premier Park Road, Park Royal, and redevelopment to provide a 25,281 sq m (GEA) data centre. Considered and resolved at the Old Oak and Park Royal Development Corporation planning committee on 26 February 2026. No power capacity figure appears in the committee papers.
View projectData centre campus, Hayes Bridge and Heathrow Interchange
77/100 · LikelyHayes, London
ApprovedData centre 97 MW · IT loadHillingdon's register records approval of hybrid application 78343/APP/2025/719: Phase 1 full permission and Phases 2 to 4 outline permission. The parent register gives 29 October 2025 as the decision date; Colt calls the October 2025 milestone a committee resolution to grant, while later council condition applications refer to permission dated 20 May 2026. The issued decision notice is needed to reconcile these dates. Construction commencement for London 6, 7 and 8 was not confirmed in the sources checked on 8 October 2026. Colt's 4 November 2025 release states 97 MW additional IT capacity and early-2029 first operation; its current undated project page states 98 MW and first-phase delivery in 2028. These conflicting operator figures and targets are retained as separate claims, not resolved estimates. The planning report's 250 MW is stated electrical demand, not IT load.
View projectDataVita DV3, Chapelhall
75/100 · LikelyDataVita
Chapelhall, Scotland
Under constructionData centre 40 MW · definition not publishedA new data centre building (DV3) at DataVita's existing Chapelhall campus in North Lanarkshire, within the Lanarkshire AI Growth Zone. Financed as part of a £300 million debt facility announced in August 2026 alongside an expansion of the adjacent, already-operating DV1 building. DatacenterDynamics reported in September 2026 that DV3 was under construction, with capacity in both buildings contracted to CoreWeave under a 15-year lease.
View projectCourt Lane Industrial Estate data centre, Iver
72/100 · LikelyIver, South East
ApprovedData centre Capacity not publishedOutline permission to demolish Court Lane Industrial Estate and build a data centre of up to 65,000 sqm (GEA). Buckinghamshire Council refused it in October 2023 on green belt, landscape and visual harm, the setting of the Grade II listed Iver Court Farmhouse and air quality. The Secretary of State allowed the recovered appeal in December 2024.
View projectAda Docklands Data Campus, Royal Docks
67/100 · LikelyAda Infrastructure
London, London
Under constructionData centre Capacity not publishedA three-building data centre campus on a former paint factory site next to Tate & Lyle in the Royal Docks. Newham's Strategic Development Committee resolved to grant the hybrid application on 20 June 2024, with detailed consent for Building 1, and permission was issued in December 2024. All three reserved matters applications were approved by May 2026, giving detailed permission for the whole site. Ada Infrastructure, part of US-based Ares Management's digital infrastructure business, broke ground on 26 February 2026 and is building the first of three 70 MW buildings (210 MW in total, measure not defined), with the first due in mid-2028. The project expects 524 construction jobs.
View projectCambois data centre campus
67/100 · LikelyQTS (Blackstone)
Cambois, North East
Under constructionData centre 720 MW · IT loadOutline planning permission, with all matters reserved, granted by Northumberland County Council on 8 May 2025 for up to ten Class B8 data centre buildings totalling up to 540,000 sqm gross internal area, plus a substation, emergency generators and ancillary structures. The council committee report states approximately 72 MW of IT capacity per building, about 720 MW across the full campus; this is recorded as IT load. Initial earthworks began in October 2025 and reserved matters for phase 1 were approved in December 2025, so the project is recorded as under construction.
View projectData centre campus, Tudor Works, Hayes
67/100 · LikelyColt Data Centre Services
Hayes, London
Under constructionData centre 31 MW · IT loadThe London Borough of Hillingdon approved application 38421/APP/2021/4045 on 26 April 2022 for redevelopment of the Tudor Works site at Beaconsfield Road, Hayes, by Colt Data Centre Services, to deliver a data centre campus of two buildings (Use Class B8) with associated energy and electricity infrastructure, plant, a security gatehouse, highway works, parking, landscaping and ancillary office use. Colt broke ground on the first building, London 4, in February 2023 and describes it as under construction with 31 MW of IT power; that operator figure is recorded here as IT load. The council register itself states no electrical capacity.
View projectSkelton Grange, Leeds
61/100 · LikelyMicrosoft
Leeds, Yorkshire and the Humber
ApprovedData centre Capacity not publishedA hybrid scheme for data centre buildings on the former Skelton Grange power station site at Stourton, Leeds, brought forward by Harworth Group with Microsoft. Leeds City Council's planning committee resolved to grant permission in April 2026, but no decision notice has been issued, so the scheme is not yet consented.
View projectMicrosoft Newport Imperial Park (CWL01), former Quinn Radiators site
60/100 · LikelyMicrosoft
Newport, Wales
ApprovedData centre 200 MW · IT loadMicrosoft's datacentre on the former Quinn Radiators factory site at Celtic Way, Imperial Park, Newport (application 24/0006). Newport City Council's planning committee unanimously approved demolition of the remaining buildings and two data centre buildings with diesel backup generators on 3 July 2024; Microsoft agreed a £104,000 walking and cycling contribution. Senedd Research (July 2026) puts the planned site at around 200 MW IT load; the planning papers give no MW figure. The site is separate from the Vantage (former NGD) campus at Imperial Park.
View projectDC01UK, South Mimms
57/100 · PossibleEquinix
South Mimms, East of England
ApprovedData centre Capacity not publishedOutline permission only. The council cites 87,000 sq m of floorspace; no IT-load or grid-connection figure has been verified. DC01UK announced the sale of the 85-acre site to Equinix on 30 October 2025, and the transaction was confirmed by Equinix's adviser, BNP Paribas Real Estate.
View projectTelehouse Inventory Estate data centre, East India Dock
57/100 · PossibleTelehouse (KDDI)
London (Blackwall), London
ApprovedData centre 65 MW · grid-connection capacityTelehouse, owned by KDDI, completed its purchase of the Inventory Estate at East India Dock for more than £220m in late October 2026, next to its London Docklands campus. The site carries outline consent, won at appeal in 2023, for a 35,000 sqm data centre. Telehouse says 65MVA of power is secured. No construction date has been announced.
View projectVantage Bridgend campus (former Ford engine plant)
57/100 · PossibleVantage Data Centers
Bridgend, Wales
ApprovedData centre Capacity not publishedBridgend County Borough Council's planning committee unanimously approved Vantage Data Centers' hybrid application (P/25/247/HYB) in October 2025, subject to 32 conditions. The consent gives full planning permission for the first data centre on the north-eastern part of the former Ford engine plant at Waterton, and outline permission for up to nine further data centres to be built over about 15 years. No power capacity figure is stated.
View projectTeesworks data centre campus (former Redcar Sinter Plant), Redcar
54/100 · PossibleRedcar, North East
ApprovedData centre Capacity not publishedA data centre campus of up to 462,419 sqm on the former Redcar Sinter Plant at Teesworks, the former Redcar steelworks. Redcar and Cleveland Council granted reserved matters (R/2025/0382/ESM) on 1 August 2025 under the site's 2022 outline permission, despite bp's objection that it clashed with the H2Teesside hydrogen plant. No end user has been confirmed: Google was reported in talks in September 2025, and Private Eye reported in June 2026 that Anthropic had agreed in principle to buy 222 acres (unsigned, not confirmed by Anthropic). In late October 2026 National Grid agreed to buy 73.3 acres at Dorman Point for a 400 kV substation of about 1.44 GW, due by the end of 2029, to power a data centre on the site. Council papers in April 2026 recorded no development on site.
View projectAiOnX Cambridge Innovation Campus, Elean Business Park, Sutton
52/100 · PossibleAiOnX (SWI Group)
Sutton, East of England
ApprovedData centre 330 MW · campus build-out capacitySWI Group plans a campus of up to 330MW at the Elean Business Park in Sutton, near Ely, branded AiOnX Cambridge Innovation Campus. The site carries a data centre permission first granted in 2008 and detailed in 2022 for up to 65,000 sqm. SWI Compute says a first 30MW phase of about 7,000 Nvidia GPUs is due online at the end of 2027. A local councillor says the 330MW scale-up may need a new planning application.
View projectAmazon Data Services, Ridgeway Distribution Centre, Iver
52/100 · PossibleAmazon Web Services
Iver, South East
ApprovedData centre Capacity not publishedBuckinghamshire Council approved Amazon Data Services UK's plans on 28 September 2026 to replace 17 industrial and warehouse units at the Ridgeway Distribution Centre, Iver, with a single two-storey data centre (about 30,525 sqm, main building about 20m high), a substation compound and a yard for 27 backup generators on a 7.3ha site. No MW figure has been published. The site is outside the green belt but in the Colne Valley Regional Park setting and an air quality management area. The Environment Agency generator permit is still to be decided.
View projectDeep Green Bradford, Listerhills Road
52/100 · PossibleDeep Green Technologies
Bradford, Yorkshire and the Humber
ApprovedData centre Capacity not publishedConsent reported May 2026, with heat reuse into the Bradford Energy Centre. A 5.6 MW figure is reported without a stated definition.
View projectKao Data Kenwood Point, Stockport
52/100 · PossibleKao Data
Stockport, North West
ApprovedData centre 40 MW · IT loadDemolition of an existing industrial and warehouse building and erection of a 25,900 sq m data centre at Kenwood Point, Stockport, with associated parking, servicing and access. Approved by Stockport Council's Heatons and Reddish Area Committee. Applicant recorded as KD 5 Limited. Kao Data's written evidence to Parliament (IGR0029, 13 January 2025) identifies 40 MW of IT capacity. This is recorded as published IT load and included in comparable IT-capacity totals; it is not a verified grid-connection capacity. Programme update checked 8 October 2026: Kao Data's dated statement of 1 July 2026 says demolition is complete and the site has been prepared; substation and power-cabling works were ongoing. Main data-centre buildings are expected to be constructed in 2027, with power anticipated in late 2027 and operation in 2028. These are operator targets, not confirmed completion dates. The older location page still gives Q3 2027; the later, dated programme clarification is used here. Main-building construction commencement is not confirmed.
View projectSembcorp Wilton International Data Centre (phase 1), former Invista site, Wilton
52/100 · PossibleDigital Reef
Redcar, North East
ApprovedData centre Capacity not publishedFull planning permission granted on 29 October 2026 (delegated decision) for phase 1 of a data centre campus at Wilton International near Redcar: data centre buildings with power, communications and support buildings, backup generators and storage tanks. The joint venture of Digital Reef and Sembcorp says phase 1 provides up to 280MW for AI and high-performance computing. EIA was screened out in April 2026.
View projectHilfield Park data centre campus (former Mercure Hotel, Tylers Way), Hertsmere (Ark Data Centres)
47/100 · PossibleArk Data Centres
Watford, East of England
Planning submittedData centre 120 MW · grid-connection capacityArk Data Centres has applied to Hertsmere Borough Council (25/1781/FUL) to clear the former Mercure Hotel site on Tylers Way, off the A41 near Watford, and build a data centre campus of free-standing data centre buildings with energy, power and water infrastructure. Ark puts the investment at more than £2.5bn. DCD reports 200MW for the campus and a 120MW power reservation at Elstree substation that passed to Ark with the site. The site is in the Green Belt and the scheme drew 1,184 objections and 4 support comments. Council officers recommended approval, but on 5 November 2026 the planning committee deferred its decision to seek more evidence on water supply from Affinity Water, further Section 106 talks and more on height and design. No new committee date has been set.
View projectArk Spring Park campus extension (Westwells Road), Neston, Corsham
45/100 · PossibleArk Data Centres
Corsham, South West
ApprovedData centre Capacity not publishedA seventh data centre building of about 27,350 sqm, up to 18.7m high, on 7.37 ha south of Ark's existing Spring Park campus. Wiltshire Council approved it in February 2026 after more than 1,100 comments, mostly objections; the legal agreements were signed in October 2026.
View projectKao Data Harlow, Plot F (KLON-07 and KLON-08)
45/100 · PossibleKao Data
Harlow, East of England
ApprovedData centre Capacity not publishedTwo further data centre buildings, KLON-07 (24,275 sq m) and KLON-08 (11,655 sq m), with a substation and ancillary offices on Plot F, north of Kao Data's existing Harlow campus. The site sits within Harlow's London Road (North) Local Development Order, which grants planning permission for data centres. Harlow Council confirmed on 24 April 2025 that the scheme complies with the order (HW/LDOC/25/00111), so it can proceed without a separate planning application. Applicant recorded as KD 6 Limited. Kao Data's own Harlow page does not yet list KLON-07 or KLON-08, and no MW figure, start date or contractor has been published.
View projectVantage CWL2 campus, Bro Tathan, St Athan
45/100 · PossibleVantage Data Centers
St Athan, Wales
ApprovedData centre 120 MW · definition not publishedA three-building data centre campus on 10.9 hectares of the former RAF St Athan airfield, north of Ffordd Bro Tathan in the Vale of Glamorgan. Vantage Data Centers, through VDC CWL21 Limited, holds planning permission for demolition and a data centre with back-up generators, plant and a substation.
View projectData centre, former White's Reclamation Site, Eccles
43/100 · PossibleEccles, North West
ApprovedData centre Capacity not publishedSalford City Council approved with conditions, on 23 July 2025, the demolition of existing structures, land remediation and redevelopment of the former White's Reclamation Site on Liverpool Road, Eccles, for an employment scheme comprising a data centre (Class B8) and ancillary office (Class E), together with substations, plant, parking, servicing, landscaping and access works. The application was determined at Planning Panel following committee consideration on 6 February 2025. The register states no electrical capacity, so none is recorded.
View projectManor Farm and land north of Wraysbury Reservoir
42/100 · PossibleSlough, South East
ApprovedData centre 72 MW · IT loadRecovered appeal (ref 3366043) allowed on 10 June 2026 by the Minister of State for Housing and Planning on behalf of the Secretary of State, granting planning permission subject to conditions. The appellant is Manor Farm Propco Limited, a subsidiary of Tritax Big Box REIT; the end operator is not identified. The decision letter and Inspector's Report record 72 MW of proposed data-centre IT capacity, together with a co-located 100 MW battery energy storage system.
View projectEquinix Wexham Road (former AkzoNobel site)
38/100 · SpeculativeEquinix
Slough, South East
ApprovedData centre Capacity not publishedOutline planning application P/00072/152 by Equinix for up to 90,614 sqm (GEA) of data centre development, with ancillary offices and a substation, on the former AkzoNobel decorative paints site off Wexham Road, Slough. On 26 November 2025 Slough Borough Council's planning committee voted to delegate approval to the Planning Manager, subject to a financial contribution of at least £200,000 (capped at £500,000) towards a Slough district heating network. Layout, scale, appearance and landscaping are reserved for later approval. Issue of the decision notice has not been confirmed. No power capacity figure is published.
View projectGoogle data centre, North Weald Airfield
38/100 · SpeculativeGoogle
North Weald, East of England
ApprovedData centre Capacity not publishedOutline application (EPF/0849/25) by Global Infrastructure UK Ltd for a Google data centre campus on 52 acres (21 ha) of North Weald Airfield, Essex: up to two data centre buildings and offices, with up to 77,148 sq m of floorspace (GEA). Epping Forest District Council's Planning Committee A voted to approve it with conditions on 10 December 2025. The officer recommendation was subject to a s106 agreement, and a decision notice has not been confirmed. Google bought the site for £88.2m in January 2024. The officer report estimated 100 to 200 direct jobs and up to 780 local jobs in total. No capacity figure has been published.
View project45 Maylands Avenue, Hemel Hempstead
36/100 · SpeculativeHemel Hempstead, East of England
ApprovedData centre Capacity not publishedOutline planning permission was reported in August 2025 for the redevelopment of 45 Maylands Avenue, Hemel Hempstead, for Northtree Investment Management: the existing two-storey warehouse and office building (currently self-storage) would be replaced by a new three-storey data centre of up to about 5,100 sq m, with ancillary offices, plant and a substation. Designed by Scott Brownrigg.
View projectBidder Street data centre, Canning Town
36/100 · SpeculativeLondon (Canning Town), London
ApprovedData centre 80 MW · IT loadAn urban hyperscale data centre on a former scrap metal recycling site on Bidder Street, Canning Town, about 500 metres from the London Internet Exchange. The scheme comprises a data centre with offices, a plant building and an energy centre for heat recovery. Legal & General, Goldacre and sineQN describe it as a £750m investment delivering 80MW of IT power.
View projectPinewood South data centre, land south of Pinewood Studios, Iver Heath
36/100 · SpeculativeIver Heath, South East
ApprovedData centre Capacity not publishedPinewood Group, through Pinewood South Ltd, applied in July 2025 for outline planning permission for a data centre of up to 55,030 sqm on land south of Pinewood Studios, Iver Heath, with construction costs of over £1 billion, a nature reserve and a community garden. Buckinghamshire Council resolved to grant permission; reports give the date as December 2025 or 25 February 2026. A decision notice has not been seen. No operator, capacity or grid connection has been published. The site is in the Slough Availability Zone.
View projectDataVita DV4, Chapelhall
35/100 · SpeculativeDataVita
Chapelhall, Scotland
Planning submittedData centre Capacity not publishedA fourth DataVita data centre building proposed for the Chapelhall campus in North Lanarkshire, within the Lanarkshire AI Growth Zone, alongside the operating DV1 and the under-construction DV3. Planning permission in principle was submitted to North Lanarkshire Council in early September 2026, with a stated construction investment of £849.6 million over two years. The maximum building height was reduced from 30 to 26 metres following community consultation feedback.
View projectKao Data Park Royal (former Frogmore Industrial Estate)
35/100 · SpeculativeKao Data
London (Park Royal), London
ProposedData centre Capacity not publishedKao Data bought the 4.7-acre former Frogmore Industrial Estate on Acton Lane in 2026 and plans a data centre to open in 2029. Plans are being prepared with OPDC; an earlier owner's data centre scheme on the site was refused by OPDC.
View projectRover Way energy park and data centre, Splott
33/100 · SpeculativeCardiff, Wales
ApprovedData centre Capacity not publishedCardiff Council granted full planning permission on 15 April 2025 for the partial removal of fill material, reprofiling groundworks and the installation of an energy park comprising a battery energy storage facility, associated substation and ancillary buildings, together with a data centre, on land at Rover Way, Splott. The Planning Committee resolved to grant on 17 October 2024 subject to a Section 106 agreement, and the decision was issued once that agreement was completed. The register does not state an electrical capacity for the data centre, so none is recorded. Latos Data Centres, which is delivering the data-centre element, stated in December 2024 that the Cardiff data centre was under construction. The associated energy park includes 1,000 MW of battery storage, which is not data-centre load.
View projectThames Valley Park Data Centre, Earley
33/100 · SpeculativeEarley, South East
Planning submittedData centre 72 MW · IT loadProperty investor Mapeley has applied to Wokingham Borough Council for outline permission to replace three office buildings on the Microsoft campus at Thames Valley Park, Earley, with a data centre of 72MW IT load and about 37,000 sqm. Peak demand would be about 110MW, but only 1.8MW of grid supply is available now, so the first phase would run on gas-fed fuel cells until a larger grid connection arrives, expected around 2037. Demolition is planned for 2027 and the first data halls for 2030, with a decision expected by March 2027. The scheme is put at more than £200m. Microsoft is not involved in the proposal and its lease is reported to end in December 2027. A petition against the scheme has several thousand signatures. No operator or tenant is named.
View projectAmazon Web Services, Plot 3 Maylands Avenue
28/100 · SpeculativeAmazon Web Services
Hemel Hempstead, East of England
Planning submittedData centre Capacity not publishedA purpose-built data centre for tape-based long-term storage proposed by Amazon Data Services UK Limited at Plot 3, Maylands Avenue, Hemel Hempstead. Submitted documents describe roof-level plant, an HVO-fuelled standby generator compound, chilled-water cooling and rooftop solar. No decision has been published.
View projectLand off Bedmond Road data centre, Abbots Langley
28/100 · SpeculativeAbbots Langley, East of England
ApprovedData centre Capacity not publishedOutline plans for a data centre of up to 84,000 sqm in two buildings up to 20m high, with a country park. Three Rivers District Council refused it in January 2024 as inappropriate green belt development with very substantial landscape harm. The Secretary of State recovered the appeal after a public inquiry and granted outline permission in May 2025.
View projectProsperity Parc, Holyhead (Anglesey)
28/100 · SpeculativeStena Line (via Anglesey Land Holdings)
Holyhead, Wales
ApprovedData centre Capacity not publishedA data centre-led redevelopment of the former Anglesey Aluminium site at Holyhead, led by Stena Line through Anglesey Land Holdings. Outline planning permission was granted by the Isle of Anglesey County Council in September 2025. Named by government as one of two constituent sites (with Trawsfynydd, Gwynedd) of the North Wales AI Growth Zone announced in November 2025.
View projectCardiff East Park and Ride data centre campus (Curtis Hall), Llanrumney
25/100 · SpeculativeCardiff, Wales
Planning submittedData centre 150 MW · grid-connection capacityCurtis Hall Ltd, the site owner, has applied to Cardiff Council for three data centres, an on-site substation and energy facilities on the 40-acre Cardiff East Park and Ride site in Llanrumney (hybrid application 26/00109/HYB). A 150MW grid connection is reported for full build-out but may not be available until between 2030 and 2034, so the developer proposes a temporary gas-fired energy centre of up to about 49.9MW, modelled to run from 2028 to 2033. In September 2026 the Welsh Government issued a holding direction, so Cardiff Council cannot grant permission while ministers consider calling it in.
View projectCX Technology Campus, Chapelcross
25/100 · SpeculativeAnnan, Scotland
Planning submittedData centre 1,000 MW · definition not publishedCX Tech has applied to Dumfries and Galloway Council for planning permission in principle for a campus of eight data centres on about 57ha of land north of the former Chapelcross nuclear power station, near Annan. It is reported at 1GW and £16.5bn, with up to 162,000 sqm of data-centre floorspace in buildings up to 40m high, built in phases from 2027 to 2035. On 16 September 2026 the Scottish Parliament backed a non-binding motion that no planning decisions should be made on hyperscale (over 50 MW) data centres until the Scottish Government publishes national planning guidance, which ministers expect around the end of 2026; local campaigners and APRS oppose the scheme. No operator or tenant is named.
View projectEra4 AI data centre, Shelford Landfill, Broad Oak, Sturry, Canterbury
25/100 · SpeculativeCanterbury, South East
ApprovedData centre Capacity not publishedSmall AI data centre (about 1,210 sqm) beside Shelford Landfill, powered by landfill gas from the neighbouring Valencia Energy Centre plus solar. Canterbury City Council planning committee approved it on 13 October 2026 after a call-in by Sturry ward councillors.
View projectManor Farm West, west of Poyle Trading Estate (three data centres)
25/100 · SpeculativeSlough, South East
Planning submittedData centre Capacity not publishedManor Farm Propco Limited, owned by Tritax Big Box, has submitted plans to Slough Borough Council for three data centres on a 23.5ha (58-acre) green belt site west of Poyle Trading Estate near Wraysbury Reservoir, next to the Manor Farm data centre approved on appeal in June 2026. The developer says it is operationally independent of the approved scheme. BBC reports the project at 199MW and says a separate application covers a cable route to Laleham substation.
View projectNscale Loughton sovereign AI data centre
25/100 · SpeculativeNscale
Loughton, East of England
ApprovedData centre Capacity not publishedNscale's Loughton, Essex site was named in the government's 2025 AI strategy as the UK's largest sovereign AI supercomputer and was due to open in 2027. Planning permission is in place, but the Guardian reported on 24 September 2026 that UK Power Networks had told Nscale it cannot supply the requested 90MW until the early-to-mid 2030s. In October 2026 Microsoft, the anchor tenant, ended its agreement for the site; Microsoft said the decision relates to this single site. Nscale says it remains committed to Loughton and is looking at alternative power sources.
View projectCaineal AI data centre, A127 / Old Nevendon Road, Wickford
18/100 · Headline onlyWickford, East of England
ApprovedData centre Capacity not publishedA £1.3bn data centre on 1.8 ha of green belt beside the A127. Basildon Council resolved to grant permission in September 2025; surveyors were reported on site in late September 2026. No capacity, grid or contractor details published.
View projectElsham Tech Park, former RAF Elsham Wolds
18/100 · Headline onlyElsham, Yorkshire and the Humber
ApprovedData centre 1,000 MW · IT loadOutline application (PA/2025/643) by Elsham Tech Park Ltd, whose parent is Greystoke Land, for an AI data centre campus of up to 1 GW of IT load on about 176 ha of land adjacent to Elsham Wolds Industrial Estate, near Scunthorpe. North Lincolnshire Council's planning committee resolved to grant permission on 11 March 2026, subject to National Highways' holding objection being resolved and a s106 agreement. A decision notice has not been confirmed. The scheme has up to 905,000 sq m of data centre floorspace across up to 15 data centre plots, battery storage, a 49.9 MW on-site energy centre and heat reuse for greenhouses. The application papers put the build cost at £5.5bn to £7.5bn; the council cites up to £10bn of private investment. The officer report gives over 600 permanent jobs; the developer has cited 900 to 1,200. Construction is expected from 2027, with the first phase open in 2029. No operator is named.
View projectHumber Tech Park, land south of the A160, South Killingholme
18/100 · Headline onlySouth Killingholme, Yorkshire and the Humber
ApprovedData centre 386 MW · definition not publishedOutline scheme by Humber Tech Park Ltd, a Greystoke Land company, for three AI-training data centre buildings, an on-site substation and a horticultural glasshouse using waste heat, on about 76 ha south of the A160 near South Killingholme. North Lincolnshire Council's planning committee approved outline application PA/2024/584 on 31 July 2024. Reported cost £2.2bn to £3bn and about 370 to 400 jobs. No end user named. Reserved matters still needed. Linked to the Northern Lincolnshire AI Growth Zone bid alongside Greystoke's Elsham Tech Park.
View projectWest London Technology Park (Woodlands Park landfill site), Iver
18/100 · Headline onlyIver, South East
PausedData centre Capacity not publishedOutline plans for a data centre of up to 72,000 sqm in two buildings on a former landfill site south of Slough Road, Iver. An earlier, larger scheme was refused in 2022 and the appeal dismissed in October 2023. The second application was refused by Buckinghamshire Council in June 2024 on green belt, landscape, air quality and habitat grounds, then allowed on appeal by the Secretary of State in July 2025 as grey belt. Campaigners Foxglove and Global Action Plan challenged the decision; in January 2026 the government admitted a "serious logical error" over the lack of an environmental impact assessment and accepted the permission should be quashed. The project is on hold pending the court outcome.
View projectData Centre Campus, Ampthill Road, Bedford
17/100 · Headline onlyBedford, East of England
ProposedData centre Capacity not publishedOn 15 June 2026 the Secretary of State issued a direction under section 35 of the Planning Act 2008 requiring this proposed data centre campus at Ampthill Road, Bedford, in Central Bedfordshire, to be consented through a Development Consent Order. This is a designation at the pre-application stage: no application has been examined or decided, and no power capacity figure is published in the direction or decision letter.
View projectSDC M40 Campus, Wapseys Wood landfill, Gerrards Cross
17/100 · Headline onlyGerrards Cross, South East
ProposedData centre 300 MW · IT loadSlough Holdings UK Limited, owned by funds managed by SDC Capital Partners, proposes a data centre campus of up to three buildings with an IT load of up to about 300MW on the Wapseys Wood landfill site between Gerrards Cross and Beaconsfield. An on-site gas-fired energy centre of about 250 to 350MW would power the campus, at least at first. Veolia owns the energy centre land and is the energy partner. The Secretary of State directed on 16 March 2026 that the scheme be treated as a nationally significant infrastructure project. The Planning Inspectorate published a scoping opinion on 9 June 2026 and expects the application in January 2027.
View projectSpodegreen Data Centre, Little Bollington
17/100 · Headline onlyLittle Bollington, North West
ProposedData centre Capacity not publishedRenewable energy firm Innova proposes a data centre campus on about 60ha (148 acres) of Tatton Estate farmland near Little Bollington, Cheshire, beside the M56. The plans include data halls, offices, a training facility, a district heat network and a solar farm. The site is in the green belt. The scheme is at public consultation only: no planning application has been made, and one is expected to go to Cheshire East Council in late 2026 or early 2027. No power capacity has been published, and no operator or tenant is named. How to find the council record: For the Spode Green proposal, Cheshire East Council lists the site as land south of Lymm Road, Little Bollington. Open Innova’s Local Plan representation 6647 in the sources below. It identifies the land as Call for Sites reference 396. A formal planning application would have a separate reference.
View project1 Redheughs Avenue data centre, South Gyle
15/100 · Headline onlyEdinburgh, Scotland
RefusedData centre 212.42 MW · definition not publishedPlanning permission in principle (25/04239/PPP) sought by Shelborn Drummond Ltd was refused by the City of Edinburgh Council's planning sub-committee in February 2026, against officer recommendation, and is now under appeal (DPEA ref PPA-230-2794). Capacity has been reported variously as 210 MW, 212 MW, 212.42 MW and 213 MW; the measure is not stated, so the figure is excluded from every capacity total.
View projectBryn Coch Business Park data centre (former Ferodo factory), Griffith's Crossing, Caernarfon
15/100 · Headline onlyCaernarfon, Wales
Planning submittedData centre Capacity not publishedOutline plans for up to five data centre buildings and substations, about 300,000 sqm, on the 41 ha former Ferodo brake factory site beside the Menai Strait. Strong local opposition, including a petition of more than 22,000 signatures and a rally in October 2026. Operator not named.
View projectEast Havering Data Centre Campus, North Ockendon
15/100 · Headline onlyNorth Ockendon, London
ProposedData centre 600 MW · definition not publishedDigital Reef, working with Havering Council, proposes a hyperscale data centre campus of up to 400,000 sq m on green belt farmland at North Ockendon, east of the M25 on the Havering/Thurrock boundary, with a 113-hectare public ecology park, battery storage, horticulture and renewable energy facilities. The developer puts the investment at £14.7bn; press and campaigners describe it as about 600MW on about 200 hectares. Instead of a planning application, the council's planning authority is using a Local Development Order: the Strategic Planning Committee approved a draft LDO for consultation on 3 March 2026 and consultation ran from 6 March to 12 April 2026. No decision on adopting the LDO has been announced.
View projectMwyndy Cross data centre, land east of A4119, Pontyclun
15/100 · Headline onlyPontyclun, Wales
Planning submittedData centre Capacity not publishedFull planning application by Talbot Green Developments for a 21,490 sqm data centre on land east of the A4119 at Mwyndy Cross, near Pontyclun. A request for Welsh Ministers to call the application in was under initial processing in October 2026. Operator, capacity and grid not stated.
View projectSpango Valley data centre campus (former IBM site), Greenock
15/100 · Headline onlyGreenock, Scotland
Planning submittedData centre Capacity not publishedSlate Island Developments has submitted a planning application to Inverclyde Council for four data centre buildings totalling about 80,000 sqm, with a separate battery storage scheme, at the former IBM site at Spango Valley, off Inverkip Road, Greenock. No power capacity has been published.
View projectDevon Data Campus (Xlinks), near Great Torrington
10/100 · Headline onlyXlinks
Great Torrington, South West
ProposedData centre 1,500 MW · IT loadXlinks proposes a campus of up to 1.5GW of AI data centre capacity plus a 1.8GW battery storage facility on about 344ha of farmland near Great Torrington in the North Devon UNESCO biosphere reserve, with an estimated £12.2–13.8bn investment. Two applications to Torridge District Council are expected; none has been submitted. Public consultation has been postponed amid strong local opposition. Xlinks says some reported details, such as a drought water-use figure, reflect an outdated design.
View projectConesby Data Centre Campus, Normanby Road, near Scunthorpe (Rivington Energy)
7/100 · Headline onlyScunthorpe, Yorkshire and the Humber
ProposedData centre Capacity not publishedProposed two-building data centre campus on about 20 acres of greenfield land off Normanby Road, partly powered by an adjoining solar farm. Rivington Energy, majority-owned by Federated Hermes, held a pre-application consultation in May 2026.
View projectDurham Technology Park (Tract), Murton / South Hetton
7/100 · Headline onlyTract
Murton, North East
ProposedData centre Capacity not publishedUS data centre park developer Tract is consulting on a seven-building campus of up to 500MW near Murton and South Hetton, County Durham, its first UK project. It plans an on-site substation near an expanding grid substation and says it will submit a planning application to Durham County Council in December 2026.
View projectEbbsfleet AI Data Centre Campus, New Barn Road, Dartford (Clearstone)
7/100 · Headline onlyDartford, South East
ProposedData centre 240 MW · IT loadProposed campus of up to four buildings on about 145 acres near Ebbsfleet. The government directed on 1 July 2026 that it be treated as nationally significant, so it will need a Development Consent Order. First building targeted for 2030; Clearstone is seeking an operator partner.
View projectLongmarsh Green Energy data centre campus, Tilney St Lawrence and Fincham, West Norfolk
7/100 · Headline onlyTilney St Lawrence, East of England
ProposedData centre 1,000 MW · definition not publishedProposed 1GW data centre campus with up to 1.3GW of solar and battery storage across two West Norfolk sites, north-east of Tilney St Lawrence and near Fincham and Barton Bendish. EPL Norfolk puts the cost at more than £25bn. Public consultation runs from 15 October to 26 November 2026.
View projectHaspielaw Farm, Hamilton
0/100 · Headline onlyHamilton, Scotland
ProposedData centre Capacity not publishedA data centre campus with ancillary offices, back-up generators, fuel storage, a battery energy storage system and an electricity substation is proposed at Haspielaw Farm, Hamilton. South Lanarkshire Council issued an environmental screening opinion on 25 June 2025 confirming an environmental impact assessment is required. This is a pre-application procedural step: no planning application for the campus has been determined.
View projectAmazon Thorney Lane data centre, Thorney Business Park, Iver
Amazon Web Services
Iver, South East
ApprovedData centre Capacity not publishedReality Score: Not yet scored
Amazon Data Services UK Limited applied to the Environment Agency for a permit (EPR/MP3824MG/A001, advertised 3 June 2026) for emergency back-up generation at a data centre on Thorney Business Park, Iver: 36 main generators of up to 7.57 MWth thermal input each, plus two house generators. The permit documents cite an extant hybrid planning permission (PL/22/1775/FA), granted by Buckinghamshire Council on 29 May 2024 to the previous site owner: full permission for a first data centre building with backup generators and outline permission for further data centre buildings. Amazon will seek design changes through a new full application. Generator thermal input is not an IT-load figure and is not recorded as capacity.
View projectArk Longcross Park data centre campus, Longcross Garden Village, Chertsey
Ark Data Centres
Longcross, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Ark Data Centres' modular campus at Longcross Park, the first commercial development in Longcross Garden Village (Runnymede), part of the Enterprise M3 Enterprise Zone. AI cloud firm Nebius signed in June 2025 (initial 4,000 Nvidia Blackwell Ultra GPUs, live November 2025) and by June 2026 had taken the whole LP01 building. In June 2026 Ark announced an £807m expansion: vertical extensions to existing buildings, infrastructure upgrades and a new 36 MW building, LP02.
View projectAtlasEdge Columbus Way, Salford
AtlasEdge
Salford, North West
PausedData centre Capacity not publishedReality Score: Not yet scored
AtlasEdge won planning permission from Salford City Council on 9 December 2022 (22/79882/FUL) for two data centre buildings and a substation on the Broadway House site, Columbus Way. The scheme never progressed and the permission has probably lapsed: in 2026 a new application (PA/2026/0599) was made for two warehouses on the same site.
View projectCarlton Park Data Centre 1 & 2, Narborough
VerifiedSantander UK Plc
Narborough, East Midlands
OperationalData centre Capacity not publishedReality Score: Not yet scored
Carlton Park Data Centre 1 & 2 at Narborough, Leicestershire is operated by Santander UK Plc and holds an Environment Agency environmental permit (EPR/QP3533ED) for its standby diesel and Diesel Rotary Uninterruptible Power Supply units. The permit regulates backup power generation plant only and states no figure for the data centres' IT load or grid connection, so no capacity is recorded.
View projectCloudHQ LHR Campus, Didcot
CloudHQ
Didcot, South East
ApprovedData centre 101 MW · IT loadReality Score: Not yet scored
A £1.9bn data centre campus by Washington DC-based CloudHQ on 37.5 acres of the former Didcot A power station grounds, welcomed by the Technology Secretary in October 2024. CloudHQ describes it as fully permitted and powered, with 101 MW of critical IT load, expandable to 300 MW, and 2.25m sq ft of space. The BBC reported 1,500 construction jobs and 100 permanent roles. Separate from Amazon's Didcot North campus on the same former power station site.
View projectCobalt Data Centre Campus (Stellium)
VerifiedStellium Datacenters
Wallsend, North East
OperationalData centre 80 MW · definition not publishedReality Score: Not yet scored
Plant replacement application recorded on a third-party aggregator.
View projectCulham AI Growth Zone
VerifiedCulham, South East
ApprovedAI growth zone 100 MW · definition not publishedReality Score: Not yet scored
The UK's first AI Growth Zone, based at Culham in Oxfordshire, announced by the Prime Minister in January 2025 as part of the AI Opportunities Action Plan. Government describes AI Growth Zones as hubs for AI-enabled data centres with improved access to power and planning support.
View projectCyrusOne LON2, Prologis Park Heathrow
CyrusOne
West Drayton, London
OperationalData centre 14 MW · IT loadReality Score: Not yet scored
CyrusOne's LON2 data centre at Prologis Park Heathrow, west of London. CyrusOne gives 14 MW of IT capacity in 7,484 sq m of technical space in one two-storey building, with active/active 11 kV dual supplies, and says it has run on 100% renewable electricity since 2021.
View projectCyrusOne LON6, Iver Heath
CyrusOne
Iver Heath, South East
ApprovedData centre 90 MW · IT loadReality Score: Not yet scored
CyrusOne's sixth UK data centre: a 63,000 sq m hyperscale facility with 90 MW of IT capacity and 30,000 sq m of technical space, on a 41-acre former landfill site in the green belt between Denham Road, Seven Hills Road and the M25, opposite Pinewood Studios. CyrusOne is owned by US investors KKR and Global Infrastructure Partners. Full planning permission was reported in July 2025. CyrusOne states investment of more than £1.2bn, about 580 construction jobs and 540 operational roles. It planned to break ground in Q3 2026 with first capacity in early 2028; John F Hunt was reported in July 2026 to have won a £20m enabling and remediation package.
View projectCyrusOne Slough data centres (LON1, LON3, LON4, LON5)
CyrusOne
Slough, South East
OperationalData centre 54 MW · IT loadReality Score: Not yet scored
Four CyrusOne data centres in Slough, near Heathrow. CyrusOne gives LON1 as 9 MW of IT capacity in 4,309 sq m, LON3 as 9 MW in 3,600 sq m, LON4 as 18 MW in 9,526 sq m and LON5 as 18 MW in 6,452 sq m: 54 MW of IT capacity in all. Its separate LON6 campus at Iver Heath is in development.
View projectDataVita DV1, Chapelhall
DataVita
Chapelhall, Scotland
OperationalData centre Capacity not publishedReality Score: Not yet scored
DataVita's first data centre at Chapelhall, North Lanarkshire, operating since 2016 and described by DataVita as Scotland's largest purpose-built Tier III certified data centre. In August 2026 DataVita secured a c.£300m debt facility, backed by a £202m National Wealth Fund guarantee (the fund's first support for UK compute), to expand DV1 and build DV3 next door. The capacity of both is contracted to CoreWeave on a 15-year lease. Part of the Lanarkshire AI Growth Zone.
View projectDigital Realty Crawley
VerifiedDigital Realty
Crawley, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Operational campus at Manor Royal. Verified through the Environment Agency permit for standby generation; the underlying planning consent was not retrieved.
View projectDigital Realty Slough (LHR26 and LHR27), Ajax Avenue, Slough Trading Estate
Digital Realty
Slough, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Two Digital Realty colocation data centres on Ajax Avenue in the Slough Trading Estate: LHR26 at 630 Ajax Avenue (about 9,150 sq m) and LHR27 at 631 Ajax Avenue (about 7,900 sq m). Digital Realty bought the site, formerly Cyxtera's Slough facility, in 2024 for a reported $200m. IT load is not published.
View projectDigital Realty Woking data centre
VerifiedDigital Realty (UK) Limited
Woking, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Digital Realty (UK) Limited operates a data centre at Kestrel Way on the Goldsworth Park Trading Estate in Woking under Environment Agency permit EPR/TP3530DV, issued on 27 February 2018. The permit decision document records 65 diesel-fuelled standby generators with an aggregated combustion capacity of 214 MW thermal. That is a heat input figure for backup plant and is not the site's IT load or grid connection, so no electrical capacity is recorded for this site.
View projectEquinix LD8, London Docklands
VerifiedEquinix
London, London
OperationalData centre Capacity not publishedReality Score: Not yet scored
Operational Equinix colocation facility in London Docklands (E14 9GE). The Environment Agency permit covers 64 MWth of standby generator thermal input, which is a heat input figure and not an IT-load capacity, so no capacity figure is recorded.
View projectEquinix Slough campus (LD4 to LD7, LD14), Slough Trading Estate
Equinix
Slough, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Equinix's main London interconnection campus on the Slough Trading Estate, including LD4 (2 Buckingham Avenue), LD5 (8 Buckingham Avenue), LD6 (352 Buckingham Avenue) and LD7. The Environment Agency permit for the "Equinix Slough Campus Data Centre" covers LD4 to LD7, and a variation granted on 29 August 2025 adds a new building, LD14, with 12 new standby generators. Equinix gives LD4 as 13,320 sqm of colocation space. No campus power figure is published by Equinix.
View projectEra4 The Mill AI data centre campus, former Liberty Steel site, Newport
Newport, Wales
ApprovedData centre 1,000 MW · campus build-out capacityReality Score: Not yet scored
Era4 plans "The Mill", an AI campus of up to 1GW (up to 400,000 Nvidia Vera Rubin GPUs at full build) on a 230-acre former Liberty Steel mill site in Newport, with modular data centre units inside existing buildings. Change of use approved in early 2026; first stage due online in 2027. Liberty Steel still operates a plant on part of the site.
View projectGlobal Switch London
VerifiedGlobal Switch
London, London
OperationalData centre 87 MW · definition not publishedReality Score: Not yet scored
Long-established operational facility. Verified through the Environment Agency permit; original borough consents not traced.
View projectGoogle Waltham Cross data centre
Google
Waltham Cross, East of England
OperationalData centre Capacity not publishedReality Score: Not yet scored
Google's first UK data centre, on a 33-acre site at Waltham Cross, Hertfordshire, which Google bought in October 2020. Construction of the $1bn (about £790m) facility was announced on 18 January 2024. It was opened by the Chancellor on 16 September 2025 as part of Google's two-year £5bn UK investment, to support Google Cloud, Workspace, Search and Maps, including AI services. Google gives no capacity figure. The site is Maxwells Farm West (Theobalds Business Park), Cheshunt, in the Borough of Broxbourne; the planning applicant for the data centre was Global Infrastructure UK Ltd.
View projectImperial Park campus, Newport (Vantage, formerly Next Generation Data)
Vantage Data Centers (formerly Next Generation Data)
Newport, Wales
OperationalData centre Capacity not publishedReality Score: Not yet scored
An operating colocation campus at Imperial Park, Coedkernew, near Newport, built as Next Generation Data and acquired by Vantage Data Centers in July 2020, since marketed by Vantage under its Cardiff campus branding. It is a separate site from the Vantage Bridgend scheme and from the Rover Way project in Cardiff. In August 2026 Vantage announced that Nebius will deploy high-density AI capacity at the Newport campus, the first customer commitment in the South Wales AI Growth Zone (no MW figure published).
View projectIron Mountain LON-1, Dundee Road, Slough
Iron Mountain Data Centers
Slough, South East
OperationalData centre Capacity not publishedReality Score: Not yet scored
Iron Mountain's LON-1 colocation data centre at 724-729 Dundee Road on the Slough Trading Estate, a former banking data centre that Iron Mountain has upgraded. Iron Mountain gives 10,400 sqm across four data halls on a 4.5-acre campus and 8.75 MW of "total power capacity" (not defined as IT load). Iron Mountain says it runs two further London sites, LON-2 and LON-3.
View projectKao Data Harlow campus (KLON-01 to KLON-03), London Road, Harlow
Kao Data
Harlow, East of England
OperationalData centre 20 MW · IT loadReality Score: Not yet scored
Kao Data's AI-focused campus on the former STC/Nortel research site at London Road, Harlow, operating since 2018. KLON-01 opened in 2018; KLON-02 (10 MW) was completed and operational on 28 November 2023. A third building, KLON-03 (17.6 MW), is under construction, with its backup generators covered by an Environment Agency permit variation. Plot F (KLON-07 and KLON-08) on Harlow Innovation Park is a separate record.
View projectLanarkshire AI Growth Zone
VerifiedDataVita, in partnership with CoreWeave
Airdrie, Scotland
ApprovedAI growth zone 500 MW · definition not publishedReality Score: Not yet scored
Scotland's AI Growth Zone, delivered by data centre company DataVita around its Airdrie site in partnership with AI cloud firm CoreWeave. Government states £8.2 billion of private investment is committed, supporting more than 3,400 jobs and including a renewables park alongside the data centres.
View projectLatos edge data centre, Bower Street, Newton Heath
Manchester, North West
Planning submittedData centre Capacity not publishedReality Score: Not yet scored
Latos Data Centres has applied to Manchester City Council for an edge data centre of about 28,000 sq ft in two buildings on a three-acre brownfield site off Bower Street, Newton Heath. Completion is targeted by 2030. No power capacity has been published.
View projectNorth East England AI Growth Zone (Cobalt Park & Blyth)
VerifiedBlackstone (via QTS) at Blyth; Nscale at Cobalt Park (Stargate UK paused April 2026)
Wallsend & Blyth, North East
ApprovedAI growth zone 1,100 MW · definition not publishedReality Score: Not yet scored
UK's second AI Growth Zone, announced in September 2025 alongside the UK-US Tech Prosperity Deal, anchored at Cobalt Park (North Tyneside) and Blyth (Northumberland). Stargate UK, a joint venture between OpenAI, Nvidia and British firm Nscale, was announced to deploy sovereign AI compute at Cobalt Park, starting with 8,000 GPUs and scaling to 31,000. OpenAI paused Stargate UK on 9 April 2026, citing energy costs and regulation, and says it could proceed if conditions allow. Blackstone has committed GBP 10bn to the Blyth site via its QTS subsidiary, with the AI Growth Zone designation creating headroom for a further GBP 20bn from other partners.
View projectNorth Wales AI Growth Zone
VerifiedWales
ApprovedAI growth zone Capacity not publishedReality Score: Not yet scored
AI Growth Zone confirmed for North Wales, which government says is uniquely positioned to draw on the potential of the UK's first small modular reactor at Wylfa. The announcement is linked to 3,450 jobs for the region.
View projectNTT London 1 data centre, Yew Tree Avenue, Dagenham
NTT Global Data Centers
Dagenham, London
OperationalData centre 32 MW · IT loadReality Score: Not yet scored
NTT Global Data Centers' London 1 campus on the former Sanofi site at Yew Tree Avenue, Dagenham. The first building (London 1A) opened in January 2021 with 12,800 sqm of data centre space and 32 MW of IT load; NTT says the campus will reach 25,600 sqm and 64 MW when fully built out. A second building was reported under construction in late 2023.
View projectSouth Wales AI Growth Zone
VerifiedVantage Data Centers and Microsoft
Bridgend, Wales
ApprovedAI growth zone 1,000 MW · definition not publishedReality Score: Not yet scored
AI Growth Zone announced for South Wales, delivered with Vantage Data Centers and Microsoft. Government states £10 billion of investment will unlock at least 5,000 jobs, including at the former Ford Bridgend Engine Plant.
View projectTeledata Wythenshawe
Datum Datacentres (formerly TeleData UK)
Manchester, North West
OperationalData centre Capacity not publishedReality Score: Not yet scored
Manchester City Council approved, under delegated powers in October 2023, the demolition of Simon House next to Teledata's Delta House in Wythenshawe and its replacement with a data centre of about 45,000 sq ft. After Datum Datacentres acquired Teledata, the building was completed as Datum MCR2 and officially opened on 26 June 2025, adjacent to the existing MCR1 facility.
View projectTelehouse London Docklands campus (North, East, West, North Two, South), Coriander Avenue
Telehouse (KDDI)
London (Blackwall), London
OperationalData centre Capacity not publishedReality Score: Not yet scored
Telehouse's Docklands campus off Coriander Avenue, Blackwall, the first purpose-built carrier-neutral colocation site in Europe and home of the London Internet Exchange (LINX) since 1994. Buildings: North (1990), East (1999), West (2010), North Two (2016) and South (Blackwall Yard, 18 MW). A sixth building, West Two, is under construction (separate record). Telehouse has also bought the adjacent Inventory Estate at East India Dock (separate record).
View projectVantage Data Centers London I (LHR1), Chandos Road, Park Royal
Vantage Data Centers
Park Royal, London
Under constructionData centre Capacity not publishedReality Score: Not yet scored
Vantage Data Centers' first London campus, on the former Chandos Road Trading Estate in Park Royal (the PowerGate area of North Acton). Two multi-storey data centres on about 2 hectares, around 430,000 sq ft in total, with Vantage quoting 48MW to 55MW of IT load and a 110MVA substation. Outline permission was granted in September 2021; OPDC's June 2024 committee report says works had started on phases 1a and 1b and recommended approving phase 2 (16,362 sq m data centre plus generator building).
View projectVIRTUS LONDON1 data centre, Enfield
VerifiedEnfield DC Service Company Limited
Enfield, London
OperationalData centre 4.2 MW · IT loadReality Score: Not yet scored
The VIRTUS LONDON1 data centre at Trade City, Crown Road, Enfield holds Environment Agency permit EPR/PP3225SX, issued on 13 September 2023 to Enfield DC Service Company Limited and covering combustion plant on the site. The permit states no electrical capacity; the 4.2 MW IT load recorded here comes from VIRTUS's current Enfield campus page (an older 2021 specification sheet gave 4.3 MW).
View projectVIRTUS LONDON2, Hayes
VIRTUS Data Centres
Hayes, London
OperationalData centre 12.3 MW · IT loadReality Score: Not yet scored
VIRTUS's LONDON2 data centre at Hayes in west London. VIRTUS gives 12.3 MW of IT capacity and over 6,000 sq m of net technical space, and says the modular facility runs on 100% renewable energy.
View projectVIRTUS Slough campus (LONDON3, 4, 9, 10, 11, 12 and 19), Slough Trading Estate
VIRTUS Data Centres
Slough, South East
OperationalData centre 145.5 MW · IT loadReality Score: Not yet scored
VIRTUS runs seven data centres on the Slough Trading Estate. Its campus page lists LONDON3 (7.2 MW), LONDON4 (26.6 MW), LONDON9 (24 MW), LONDON10 (6.6 MW), LONDON11 (13.3 MW), LONDON12 (21 MW) and LONDON19 (33.5 MW): 145.5 MW of IT load in all.
View projectVIRTUS Stockley Park campus
VerifiedVIRTUS Data Centres
Uxbridge, London
OperationalData centre Capacity not publishedReality Score: Not yet scored
Campus counted as one project. London 5 and 6 are permitted and operational; the permit was refused in part for London 7 and 8. That refusal is of the environmental permit, not necessarily of planning consent.
View projectYondr London campus (former Uxbridge Road gas works and AkzoNobel paint factory), Slough
Yondr Group
Slough, South East
OperationalData centre 100 MW · campus build-out capacityReality Score: Not yet scored
Yondr Group's 100 MW London campus at 1 Petersfield Avenue, Slough, on the former Uxbridge Road gas works and disused AkzoNobel paint factory, beside the Grand Union Canal (Slough Arm). Building 1 (30 MW) went live in July 2024; Building 2 (30 MW) brought its first 10 MW online in April 2025; Building 3 (40 MW, approved July 2024, construction from February 2025) reached its first ready-for-service milestone in May 2026. Separate from Equinix's Wexham Road scheme on another part of the former AkzoNobel land. Yondr is owned by DigitalBridge.
View project
About the UK data-centre tracker
The tracker is a register of UK data-centre and AI infrastructure projects compiled by hand. Each record holds the project name, operator where published, town and region, planning status, planning authority and reference where one exists, any published capacity figure with the measurement it refers to, and links to the documents the entry is based on.
How projects are selected
A project is added only when it can be evidenced from a named public source — a local planning portal record, a government announcement, an official statistic or an operator’s own published statement. Projects reported only through unattributed rumour are not added, and figures that have never been published are left blank rather than estimated.
What the status labels mean
- Operational
- The facility is built and in service according to its operator or an official record.
- Under construction
- Construction has started on site and this has been publicly reported or documented.
- Approved
- Planning permission or an equivalent consent has been granted, but construction has not been confirmed as started.
- Proposed
- The project has been announced or an application has been submitted, and no decision has been recorded.
How often records are checked
Records are reviewed by hand and each entry shows the date it was last verified. Projects with live planning applications are revisited more often than settled operational sites. The “checked in the last 90 days” figure above shows how much of the register has been reviewed recently.
Reporting a correction
If a record is wrong or out of date, tell us and we will check it against the source. See the corrections policy or read the research methodology. For the electricity side of this picture, see the UK data-centre electricity demand evidence and the UK AI Energy Index.
Where these projects are
Markers reflect your current filters. Select one to see the project and open its full profile.
For the wider view, see our UK data centre map.
Schematic locator map. Solid markers use coordinates recorded with the entry; dashed markers sit at the centre of the project's region because no site coordinates have been published. Nothing here should be read as a precise site boundary.
Selected project
Select a marker to see the project, its published capacity and a link to the full profile.
On the map
Where are data centres being built in the UK?
Of the 94 published data-centre facility records here, 7 are under construction and 59 more are approved, submitted for planning or proposed. These counts cover every published record, whatever filters are set above. This is an evidence-led register of projects identified from public records. It is not claimed to be a complete census of every UK data centre.
UK data centre projects under construction
| Project | Location | Latest evidenced works | Delivery firm and role | Source date | Links |
|---|---|---|---|---|---|
| Ada Docklands Data Campus, Royal Docks | London | Foundations and pilingGroundbreaking; piling for foundations started after site clearance. |
| 26 February 2026 | Profile · Source |
| Cambois data centre campus | Cambois, North East | Foundations and pilingGround improvement and CFA piling for data centres 1 and 2 and the guard house. |
| 6 August 2026 | Profile · Source |
| Data centre campus, Tudor Works, Hayes | Hayes, London | Works stage not statedGroundbreaking on London 4, the first building. | Not publicly documented | 28 February 2023 | Profile · Source |
| DataVita DV3, Chapelhall | Chapelhall, Scotland | Works stage not statedReported under construction; DataVita says it is building DV3 itself. | Not publicly documented | 3 September 2026 | Profile · Source |
| Pure DC LON01 B2, Brent Cross | London (Brent Cross), London | Foundations and pilingPiling began for the west shell. |
| 3 September 2026 | Profile · Source |
| Telehouse West Two, London Docklands campus | London (Blackwall), London | Building structurePiling and ground-floor slab complete; steelwork installation started. | Not publicly documented | July 2026 | Profile · Source |
| Vantage Data Centers London I (LHR1), Chandos Road, Park Royal | Park Royal, London | No dated works evidence recorded. | Not publicly documented | Not available | Profile |
Every published record with the status under construction appears here. Works stages keep enabling works apart from foundations and building structure. Firms are listed only where the developer, the firm or a public body has named them and their role; a blank does not mean no contractor has been appointed.
Planned and under-construction projects by region
- South East: 9 approved, 4 proposed or in planning
- East of England: 8 approved, 4 proposed or in planning
- London: 5 under construction, 4 approved, 2 proposed or in planning
- Wales: 6 approved, 3 proposed or in planning
- Scotland: 1 under construction, 4 proposed or in planning
- Yorkshire and the Humber: 4 approved, 1 proposed or in planning
- North East: 1 under construction, 2 approved, 1 proposed or in planning
- North West: 2 approved, 2 proposed or in planning
- South West: 1 approved, 1 proposed or in planning
- Northern Ireland: 1 approved
See every recorded location on the UK data centre map, or check projects that were refused, withdrawn or appealed.
Tracker totals
Totals for the 94 data-centre projects recorded in this tracker. They are not totals for the whole UK: the register covers projects we have been able to evidence from public records. 5 AI Growth Zones are designated areas rather than facilities and are excluded from these figures.
- Operational
- 25
- Under construction
- 7
- Approved
- 37
- Planning submitted
- 11
- Proposed
- 11
- Refused
- 1
- Paused
- 2
Known operational capacity: 282 MW of published IT load across 7 of 25 operational projects.
Known pipeline capacity: 4,543 MW of published IT load across 14 pipeline projects. By stage: under construction 751 MW, approved 1,680 MW, planning submitted 72 MW, proposed 2,040 MW.
- 66 of 94 records have no capacity figure that can be used in a total. A missing figure means none has been published; it is not zero and it is excluded from every sum.
- Only figures measuring the same thing are added together. IT load, stated electrical demand, grid-connection capacity and whole-campus build-out figures are kept apart. 13 records report megawatt figures with no published definition, so they are excluded.
Projects by area
Each project is counted in one area only. Slough and the Thames Valley is counted separately from the rest of South East England, so the two do not overlap.
| Area | Projects | Operational | Pipeline | Published IT load |
|---|---|---|---|---|
| London | 19 | 8 | 11 | 270.5 MW (7 of 19) |
| East of England | 14 | 2 | 12 | 20 MW (1 of 14) |
| South East England | 13 | 3 | 9 | 731 MW (4 of 13) |
| Wales | 10 | 1 | 9 | 200 MW (1 of 10) |
| North East England and Yorkshire | 10 | 1 | 9 | 1,720 MW (2 of 10) |
| Slough and the Thames Valley | 10 | 6 | 4 | 343.5 MW (4 of 10) |
| Scotland | 7 | 1 | 5 | Not published |
| North West England | 6 | 1 | 4 | 40 MW (1 of 6) |
| South West England | 2 | 0 | 2 | 1,500 MW (1 of 2) |
| Midlands | 2 | 2 | 0 | Not published |
| Northern Ireland | 1 | 0 | 1 | Not published |
Capacity columns show published IT load only, and only where a figure exists. Projects whose location has not been confirmed are grouped under “Region not confirmed” rather than being assigned to an area.
UK data centres by nation
Counts cover every published record in the tracker, not the filtered selection above.
England
76 tracked data-centre projects: 23 operational, 6 under construction, 30 approved and 15 proposed.
4,625 MW of published IT load across 20 of 76 projects.
Scotland
7 tracked data-centre projects: 1 operational, 1 under construction, 0 approved and 4 proposed.
No published IT load figures are available for these projects.
Wales
10 tracked data-centre projects: 1 operational, 0 under construction, 6 approved and 3 proposed.
200 MW of published IT load across 1 of 10 projects.
Northern Ireland
1 tracked data-centre project: 0 operational, 0 under construction, 1 approved and 0 proposed.
No published IT load figures are available for these projects.
Coverage and data quality
- Sources: every tracked project carries at least one linked public source.
- Review interval: records are re-checked at least every 180 days. No record is currently past that interval.
- Capacity definitions: 13 records carry megawatt figures the source does not define. They are shown on the project profile but excluded from totals.
Regional hubs
Summaries of tracked projects, disclosed capacity and stated investment by nation and region.
- East Midlands
- East of England
- London
- North East
- North West
- Northern Ireland
- Scotland
- South East
- South West
- Wales
- Yorkshire and the Humber
AI Growth Zones
Government-designated zones get a dedicated profile covering investment, power and grid, planning and a sourced progress timeline.
Open the Growth Zones hubHow this register is compiled
Every project is entered manually from a named public source — a planning portal record, an operator announcement or an official statistic. Confidence levels flag how firm the detail is, and figures that have never been published stay blank rather than being estimated. See our research methodology and corrections policy.
Monthly intelligence
The Real Pipeline — monthly
Which UK data-centre projects moved, and why. One email a month.