BridgendVantage CWL4, former Ford engine plant
Tracker status: Approved- Planning decision
- Hybrid permission P/25/247/HYB granted by the Development Control Committee on 2 October 2025: full permission for the first data centre building and outline permission for up to nine more.
- Physical works evidenced
- Legally commenced: Vantage's statutory notices, added to the council's register on 25 May 2026, state that development has commenced. The notices do not describe the works, and we have found no primary record of construction of the first data hall building.
- Published power figures
- No IT load, electrical demand or connection capacity has been published. The officers' report describes an interim power solution for about five years.
- Next evidenced milestone
- Permanent National Grid connection expected in late 2031, according to the officers' report; the grid upgrades need separate Section 37 consent. No completion date for the first building has been published.
Evidence: