Cardiff East Park and Ride data centre campus (Curtis Hall), Llanrumney

Cardiff, WalesPlanning submitted

Curtis Hall Ltd, the site owner, has applied to Cardiff Council for three data centres, an on-site substation and energy facilities on the 40-acre Cardiff East Park and Ride site in Llanrumney (hybrid application 26/00109/HYB). A 150MW grid connection is reported for full build-out but may not be available until between 2030 and 2034, so the developer proposes a temporary gas-fired energy centre of up to about 49.9MW, modelled to run from 2028 to 2033. In September 2026 the Welsh Government issued a holding direction, so Cardiff Council cannot grant permission while ministers consider calling it in.

Reality Score

25Speculative
How we score
Planning8/25
Grid connection0/25
Land and funding10/20
Delivery team0/15
Momentum7/15

Key facts

Operator / developer
Curtis Hall Ltd
Location
Cardiff, Wales, United Kingdom
Status
Planning submitted
Facility type
Data centre
AI relevance
Not stated

Power & grid

Published capacity
  • 150 MW — Published grid-connection capacityThe connection capacity secured or applied for, which is not the same as demand.
Share of UK tracked capacity
40.5% of published grid-connection capacity
Power
150MW grid connection reported for full build-out, possibly 2030-2034; no connection offer evidenced.
On-site generation
Temporary gas energy centre up to 47MW (development description) or 49.9MW (air quality assessment), modelled Jul 2028 to Jul 2033; fuel cells under consideration.

Planning

Planning route
Local planning (TCPA)
Planning reference
26/00109/HYB
Planning decision
Hybrid application 26/00109/HYB submitted; Welsh Government holding direction Sep 2026; undetermined.

Timeline

  1. Plans reported for a data centre campus on the Cardiff East Park and Ride site, Llanrumney.

    Source
  2. Welsh Government holding direction reported: Cardiff Council cannot grant 26/00109/HYB while ministers consider calling it in.

    Source
  3. Temporary gas energy centre (up to about 49.9MW, 2028 to 2033) reported while the 150MW grid connection is awaited.

    Source

Sources

Last verified

28 October 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.