Methodology

The Reality Score

A 100-point, evidence-led assessment of whether an announced UK data-centre project is moving towards construction.

Five factors, 100 points

Planning

/25
  • Full consent — 25
  • Outline, hybrid or resolution to grant — 18
  • Application submitted or appeal live — 8
  • Nothing filed — 0

Grid connection

/25
  • Offer or supply dated before 2030, or capacity stated as secured — 25
  • Dated 2030–33, interim-only or undated reservation — 12
  • No evidence or after 2033 — 0

Land and funding

/20
  • Land owned plus named operator or committed financing — 20
  • Land controlled or funding announced but not closed — 10
  • None shown — 0

Delivery team

/15
  • Main contractor appointed or construction under way — 15
  • Design team named — 8
  • None — 0

Momentum

/15
  • Site works, site hiring or new Companies House charges in the last 90 days — 15
  • Dated activity in the last 6 months — 7
  • Nothing for 6+ months — 0

Score bands and supplier implications

ScoreBandWhat it means for a supplier
80–100BuildingMain contractors are buying now. Approach the main contractor and M&E contractor.
60–79LikelyPackages tender within 6–18 months. Get onto the design team's radar.
40–59PossibleWatch. Early relationship with the developer only.
20–39SpeculativeDon't spend sales time yet.
0–19Headline onlyAnnouncement with no evidence behind it.

Rules we apply

  • Every point is backed by a public source.
  • No evidence, no points.
  • Every score is dated and re-checked.
  • Developers can send corrections with evidence.
  • No one can pay for a score.
  • Editorial scores are independent of paid work.