Planning
/25- Full consent — 25
- Outline, hybrid or resolution to grant — 18
- Application submitted or appeal live — 8
- Nothing filed — 0
Methodology
A 100-point, evidence-led assessment of whether an announced UK data-centre project is moving towards construction.
A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.
A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement. Always check each project's status and named delivery team.
| Score | Band | What it means for a supplier |
|---|---|---|
| 80–100 | Strong evidence | Strong public evidence across most factors. Check the project's actual status and whether a main contractor has been named before approaching; the score does not show that packages are out to tender. |
| 60–79 | Likely | Good evidence on several factors. Where a design team is named, an early introduction may be worthwhile; timing depends on the project's own milestones. |
| 40–59 | Possible | Watch. Early relationship with the developer only. |
| 20–39 | Speculative | Don't spend sales time yet. |
| 0–19 | Headline only | Announcement with no evidence behind it. |