Planning
/25- Full consent — 25
- Outline, hybrid or resolution to grant — 18
- Application submitted or appeal live — 8
- Nothing filed — 0
Methodology
A 100-point, evidence-led assessment of whether an announced UK data-centre project is moving towards construction.
| Score | Band | What it means for a supplier |
|---|---|---|
| 80–100 | Building | Main contractors are buying now. Approach the main contractor and M&E contractor. |
| 60–79 | Likely | Packages tender within 6–18 months. Get onto the design team's radar. |
| 40–59 | Possible | Watch. Early relationship with the developer only. |
| 20–39 | Speculative | Don't spend sales time yet. |
| 0–19 | Headline only | Announcement with no evidence behind it. |