Hilfield Park data centre campus (former Mercure Hotel, Tylers Way), Hertsmere (Ark Data Centres)

Ark Data Centres

Watford, East of EnglandPlanning submitted

Ark Data Centres has applied to Hertsmere Borough Council (25/1781/FUL) to clear the former Mercure Hotel site on Tylers Way, off the A41 near Watford, and build a data centre campus of free-standing data centre buildings with energy, power and water infrastructure. Ark puts the investment at more than £2.5bn. DCD reports 200MW for the campus and a 120MW power reservation at Elstree substation that passed to Ark with the site. The site is in the Green Belt and the scheme drew 1,184 objections and 4 support comments. Council officers recommend approval, and the planning committee is due to decide it on 5 November 2026.

Reality Score

47Possible
How we score
Planning8/25
Grid connection12/25
Land and funding20/20
Delivery team0/15
Momentum7/15

Early stage: worth a watching brief.

Supplying this project? See the Market Entry Sprint →

Key facts

Operator / developer
Ark Data Centres
Location
Site of former Mercure Hotel and land to south east, Tylers Way, Watford, WD25 8JH, East of England, United Kingdom
Status
Planning submitted
Facility type
Data centre
AI relevance
Not stated
Floor area
137,900 m²
Stated investment
£2,500,000,000

Power & grid

Published capacity
  • 120 MW — Published grid-connection capacityThe connection capacity secured or applied for, which is not the same as demand.
  • 200 MW — Published campus build-out capacityA whole-campus figure covering all phases. It is not current operational capacity.
  • 200 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
Share of UK tracked capacity
32.4% of published grid-connection capacity
Power
200MW reported for the campus (DCD). 120MW power reservation at Elstree substation transferred to Ark with the site sale (DCD); no connection date evidenced. Ark says a direct grid connection separate from local homes.

Planning

Planning route
Local planning (TCPA)
Planning reference
25/1781/FUL
Planning decision
Full application 25/1781/FUL registered Dec 2025; officers recommend approval; planning committee 5 Nov 2026; undetermined.
Green belt
Yes
Recorded objections
1,184
Recorded support
4

Timeline

  1. Ark Data Centres launches public consultation on a data centre campus on the former Mercure Hotel site.

    Source
  2. Full application 25/1781/FUL registered by Hertsmere Borough Council (week of 15 to 28 Dec 2025).

    Source
  3. Officers recommend approval; planning committee to decide on 5 Nov 2026 (1,184 objections).

    Source

Sources

Last verified

31 October 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.