Every change to a published indicator, reading, edition or to the methodology itself is recorded here. Corrections are also handled under our corrections policy.
updatedc_project·23 Nov 2026
Reality Score for Premier Park data centre, Park Royal, raised from 71 to 78
71 (Likely) → 78 (Likely)
Planning moved from 18 to 25: OPDC issued full permission for application 25/0196/FUMOPDC on 3 July 2026 (delegated decision), replacing the earlier resolution to grant.
updatedc_project·23 Nov 2026
Reality Score for Kao Data Park Royal (former Frogmore Industrial Estate), raised from 20 to 35
20 (Speculative) → 35 (Speculative)
Planning moved from 0 to 8 and momentum from 0 to 7: a hybrid application (26/0198/FUMOPDC) for a 12,869 sqm data centre was validated by OPDC on 9 November 2026, target decision 7 February 2027.
updateindicator·4 Nov 2026· methodology v1
UK business AI adoption: indicator confidence aligned with its latest reading
high → medium
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre electricity consumption, Great Britain: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
GB peak electricity demand: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre share of Slough grid electricity consumption: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Slough share of GB data-centre electricity consumption: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre electricity consumption, Slough: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
London and South East combined share of GB data-centre consumption: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre electricity consumption, South East: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre electricity consumption, London: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Growth in GB data-centre electricity consumption, 2020 to 2024: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Change in GB data-centre electricity consumption, 2020 to 2024 (absolute): indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
updateindicator·4 Nov 2026· methodology v1
Data-centre share of Great Britain grid electricity consumption: indicator confidence aligned with its latest reading
medium → high
The indicator-level confidence shown in the update schedule disagreed with the confidence of its latest published reading.
correctionpage·4 Nov 2026
LED bulb comparison corrected in household appliances guide
An LED bulb hour ≈ 10 AI prompts → A single LED bulb burning for an hour (~0.01 kWh) uses about as much as 33 typical AI text prompts.
Comparison now calculated from the site's per-prompt energy figure; the earlier figure was wrong.
correctionpage·4 Nov 2026
4K TV comparison corrected in household appliances guide
An hour of 4K TV ≈ 200 AI prompts → An hour of large 4K TV uses around 0.2 kWh — comparable to roughly 670 AI text prompts.
Comparison now calculated from the site's per-prompt energy figure; the earlier figure was wrong.
restatementdatapoint·3 Nov 2026· methodology v1
GB peak electricity demand: 2023 reading labelled with its definition
58 GW → 58 GW (underlying total-system peak, Clean Power 2030)
The 2023 figure and the winter 2025/26 reading use different definitions, so no percentage change is shown between them. The value itself is unchanged.
creatededition·3 Nov 2026· methodology v1
November 2026 edition published (version 1 methodology)
— → 5 new datapoints linked
Adds NESO Ten Year Outlook 2026, NESO FES 2025 2030 forecast, GB 2025 demand, winter 2025/26 peak National Demand and ONS business AI adoption. The September 2026 baseline edition is unchanged.
createddatapoint·3 Nov 2026· methodology v1
GB peak electricity demand: winter 2025/26 reading added
— → 47.3 GW (peak National Demand, 5 Jan 2026)
NESO Winter Review 2025/26 (June 2026). Transmission-measured National Demand; the earlier 58 GW (2023) is an underlying total-system figure on a different definition.
createddatapoint·3 Nov 2026· methodology v1
GB data-centre electricity demand: NESO Ten Year Outlook 2026 reading added
— → 14.6 TWh (2031)
NESO's Ten Year Outlook 2026 (presented 22 Sep 2026, slide 17) gives 5.4 TWh in 2026, 14.6 TWh in 2031 and 23.5 TWh in 2036, lower than its 2025 forecast because of updated utilisation and attrition data. The 2025 and Clean Power 2030 figures stay as earlier positions.
updatedc_project·3 Nov 2026
Reality Score for the Tudor Works data centre campus, Hayes, lowered from 75 to 67
75 (Likely) → 67 (Likely)
Momentum moved from 15 to 7. The July 2026 transformer installations are now more than 90 days old and no newer dated site works, hiring or charges have been found; the activity is still within six months.
updateindicator·3 Nov 2026· methodology v1
GB peak electricity demand: caveat added on age and definition
Capacity caveat only → Notes the 2023 base year and the different transmission-demand definition used for recent winter peaks
Avoids confusion with the ~45 GW winter 2025/26 transmission peak cited in our Ofgem reforms article.
source changeindicator·3 Nov 2026· methodology v1
GB total annual electricity demand: method note corrected to match its source
NESO Clean Power 2030, Annex 1, section 2.1.1 → NESO Ten Year Outlook 2026 (EMAC, 22 Sep 2026, slide 13)
The 269 TWh (2025) reading comes from the Ten Year Outlook 2026; the method note still cited the earlier Clean Power 2030 source.
createddatapoint·1 Nov 2026· methodology v1
UK business AI adoption: first reading added
— → 29% (June 2026)
ONS BICS wave 159 (published 2 July 2026): 29% of businesses used at least one AI technology, up 8 points on June 2025.
updatedc_project·26 Oct 2026
Reality Score for Bryn Coch Business Park data centre, Caernarfon, raised from 8 to 15
8 (Headline only) → 15 (Headline only)
Momentum moved from 0 to 7: a request for Welsh Ministers to call in Gwynedd application C25/0740/20/EIA was lodged on 24 September 2026 and is under initial processing (Welsh Government register, 16 Oct 2026), which is dated activity within six months.
updatedc_project·23 Oct 2026
Reality Score for Nscale Loughton sovereign AI data centre, Loughton, lowered from 35 to 25
35 (Speculative) → 25 (Speculative)
Land/funding moved from 10 to 0. Microsoft, the agreed anchor tenant on which the announced funding rested, has withdrawn, and grid power is not expected until the early-to-mid 2030s; no replacement funder has been named.
updatedc_project·19 Oct 2026
Reality Score for Pure DC LON01 B2, London (Brent Cross), raised from 75 to 100
75 (Likely) → 100 (Building)
Grid factor moved from 0 to 25. Pure DC has installed the final transformer at its 150MVA LON01 substation, which is stated to supply both B1 and B2, with campus energisation expected in late October 2026 (DCD and Blackridge Research, 16 Oct 2026).
correctiondc_project·15 Oct 2026
Reality Score for Kao Data Kenwood Point, Stockport, lowered: delivery team points removed
67 (Likely); delivery team 15 → 52 (Possible); delivery team 0
Kao Data's dated statement (1 July 2026) says construction of the buildings will begin when power is delivered in late 2027. No main contractor or design team has been named, so the project does not meet the test for delivery team points.
updatedc_project·13 Oct 2026
IT load for Colt London 6, 7 and 8, Hayes Bridge, recorded as 97 MW
Not recorded → 97 MW IT load
Colt's dated announcement of 4 November 2025 states 97 MW of additional IT power for London 6, 7 and 8; its undated project page says 98 MW, so the lower dated figure is used.
updatedc_project·13 Oct 2026
IT load for Kao Data Kenwood Point, Stockport, recorded as 40 MW
Not recorded → 40 MW IT load
Kao Data's written evidence to Parliament (13 January 2025) defines the 40MW Stockport figure as IT capacity.
updatedc_project·12 Oct 2026
Reality Score for Cambois data centre campus, Cambois, raised from 53 to 60
53 (Possible) → 60 (Likely)
Momentum moved from 0 to 7 after review: reserved matters for phase two data centre buildings were lodged with Northumberland County Council in September 2026, and an application for temporary substations for early operation of the campus was advertised in September 2026.
correctiondc_project·12 Oct 2026
Reality Score for Cambois data centre campus, Cambois, returned from 60 to 53
60 (Likely) → 53 (Possible)
Momentum returned to 0 pending confirmation from a primary source. The earlier rise rested on one news report and was applied before our evidence checks were complete.
updatedc_project·12 Oct 2026
Reality Score for Kao Data Kenwood Point, Stockport, raised from 60 to 67
60 (Likely) → 67 (Likely)
Momentum moved from 0 to 7: Kao Data's statement dated 1 July 2026 confirms on-site substation and power cabling work is ongoing, which is dated activity within the last six months.
updatedc_project·12 Oct 2026
Reality Score for Cambois data centre campus, Cambois, raised from 53 to 60
53 (Possible) → 60 (Likely)
Momentum moved from 0 to 7: Northumberland County Council advertised an application (26/02818/FUL, notice 4 Sep 2026) for temporary substations for early operation of the campus, and reserved matters for phase two buildings were lodged in September 2026.
updatedc_project·8 Oct 2026
Reality Score for Premier Park data centre, Park Royal, London, raised from 63 to 71
63 (Likely) → 71 (Likely)
Team factor moved from 0 to 8. Architect Scott Brownrigg states the scheme was designed by it for the Pure Data Centres Group and SEGRO joint venture (5 May 2026), confirmed by Construction Enquirer the same day. No main contractor has been named.
correctiondc_project·7 Oct 2026
Council decision date for 1 Redheughs Avenue, Edinburgh, corrected
4 February 2026 → 9 February 2026
The appeal case file gives 9 February 2026 as the date of the council's decision. 4 February 2026 was the date of the committee meeting that refused the application.
updatedc_project·7 Oct 2026
Reality Score for 1 Redheughs Avenue, Edinburgh, raised from 8 to 15
8 (Headline only) → 15 (Headline only)
Momentum raised from 0 to 7: the appeal case file shows the appellant confirmed on 12 August 2026 that it will submit an EIA Report, which is dated activity within the last six months. The appeal has been recalled by Scottish Ministers and is on hold.
correctiondc_project·7 Oct 2026
Status of the Rover Way data centre, Cardiff, changed from under construction to approved
Under construction → Approved
The under-construction status rested on November 2024 announcements that work would start immediately, made before planning permission was issued on 15 April 2025. We have found no later public evidence of construction on site.
correctiondc_project·7 Oct 2026
Planning status of Equinix Wexham Road, Slough, corrected
Reserved matters for phase 1 (P/00072/108) approved 26 November 2025 under outline P/00072/096 → Outline application P/00072/152 approved by committee on 26 November 2025, subject to a legal agreement; details reserved
The council's minutes and agenda item for 26 November 2025 show the committee considered Equinix's outline application P/00072/152. Our correction of 29 September 2026 wrongly attributed the decision to an earlier reserved-matters application.
updatedc_project·7 Oct 2026
Reality Score for the Tudor Works data centre campus, Hayes, raised from 60 to 75
60 (Likely) → 75 (Likely)
Momentum raised from 0 to 15: the operator's construction timeline records two 56 MVA transformers installed in July 2026. The site is still under construction.
updatedc_project·7 Oct 2026
Reality Score for DC01UK, South Mimms, revised from 53 to 57
53 (Possible) → 57 (Possible)
Grid lowered from 25 to 12: the operator states National Grid has scheduled connection for 2031 (previously reported as October 2029). Land and funding raised from 10 to 20: Equinix completed purchase of the campus in October 2025. Momentum raised from 0 to 7: surveys completed in August 2026 and first reserved matters submitted.
updatedc_project·7 Oct 2026
Reality Score for Skelton Grange, Leeds, raised from 53 to 61
53 (Possible) → 61 (Likely)
Momentum raised from 7 to 15: Harworth Group's half-year results of 9 September 2026 state that enabling works are ongoing. No decision notice has been evidenced.
updateindicator·6 Oct 2026· methodology vv1.0
Updated the source and schedule notes on four NESO forecast indicators (2030, 2035 and 2050 data-centre demand and the NESO modelled estimate)
2050 demand indicator: annual update → 2050 demand indicator: updated when the source publishes
NESO's FES 2025 methodology states that Future Energy Scenarios move to a three-yearly cycle for major updates, and NESO now publishes a yearly Ten Year Outlook. The 2035 and 2050 notes also now cite the FES 2025 Data Workbook.
updatedatapoint·5 Oct 2026· methodology vv1.0
Replaced "just over 20 TWh" with the exact FES 2025 ten-year forecast for 2030: 20.1 TWh
Just over 20 TWh (5.2 GW connected capacity; modelled range 3.7 to 6.3 GW) → 20.1 TWh (5.2 GW connected capacity; modelled range 3.7 to 6.3 GW)
NESO's FES 2025 Data Workbook (figure F.47) gives the Ten Year Forecast value for 2030 as 20,099 GWh.
correctiondatapoint·5 Oct 2026· methodology vv1.0
Corrected the FES 2025 range for Great Britain data-centre electricity demand in 2035 from 30 to 41 TWh to 20 to 41 TWh
30 to 41 TWh (Ten Year Forecast 33; Hydrogen Evolution 30; Electric Engagement 41) → 20 to 41 TWh (Falling Behind 20; Hydrogen Evolution 30; Ten Year Forecast 33; Holistic Transition 37; Electric Engagement 41)
The earlier reading listed three of the five FES 2025 scenarios. NESO's FES 2025 Data Workbook (figure F.47) also gives Holistic Transition at 37 TWh and Falling Behind, which does not reach net zero, at 20 TWh.
correctiondatapoint·5 Oct 2026· methodology vv1.0
Corrected the FES 2025 range for Great Britain data-centre electricity demand in 2050 from 51 to 71 TWh to 30 to 71 TWh
51 to 71 TWh (Hydrogen Evolution 51; Electric Engagement 71) → 30 to 71 TWh (Falling Behind 30; Hydrogen Evolution 51; Holistic Transition 65; Electric Engagement 71)
The earlier reading listed only two of the four FES 2025 scenarios. NESO's FES 2025 Data Workbook (figure F.47) also gives Holistic Transition at 65 TWh and Falling Behind, which does not reach net zero, at 30 TWh.
createddatapoint·5 Oct 2026· methodology vv1.0
Added NESO's FES 2025 ten-year forecast for Great Britain data-centre electricity consumption in 2030: just over 20 TWh
— → Just over 20 TWh (5.2 GW connected capacity)
NESO's written evidence to the Environmental Audit Committee gives its FES 2025 ten-year forecast for 2030. It is a later NESO forecast than the 22 TWh Clean Power 2030 figure, which stays published as the November 2024 position.
correctiondc_project·29 Sept 2026
Corrected the planning status of Equinix Wexham Road, Slough (P/00072/108) from a new outline permission to reserved matters approval for phase 1
Outline planning permission granted at Planning Committee, 26 November 2025 → Reserved matters (phase 1) approved at Planning Committee, 26 November 2025, under outline permission P/00072/096 granted 19 November 2020
The council's agenda item describes P/00072/108 as approval of reserved matters following outline approval P/00072/096 of 19 November 2020. The record wrongly described it as a new outline permission.
correctiondc_project·29 Sept 2026
Corrected the Lanarkshire AI Growth Zone community fund from up to £540 million to up to £543 million
Up to £540 million → Up to £543 million over 15 years
GOV.UK's announcement of 29 January 2026 states a community fund of up to £543 million over 15 years.
correctiondc_project·29 Sept 2026
Revised the published IT load for VIRTUS LONDON1, Enfield, from 4.3 MW to 4.2 MW
4.3 MW IT load → 4.2 MW IT load
The operator page previously cited no longer exists. VIRTUS's current Enfield campus page states 4.2 MW of IT load; an older 2021 specification sheet states 4.3 MW. The current operator statement is used.