London
○Insufficient evidenceEvidence collection has begun for London but no pressure rating can be published. The published methodology does not yet define what separates Low, Moderate, High and Severe pressure, and both current evidence records come from a single publisher and describe individual grid supply points rather than the capital as a whole. A national connection-queue total cannot be used to fill that gap.
- Connection demand
- No London-specific connection-queue figure has been established. The 125 GW Great Britain queue figure is national and is not apportioned to any region.
- Known delays
- No published average connection waiting time for London has been established. Individual delayed projects are not used to infer one.
- Network constraints
- UK Power Networks records Bow (E15) as expected to be overloaded under an N-1 outage condition from winter 2026 because of limited transformer capacity, and records a capacity deficiency in the adjoining SSEN network in West London affecting Willesden Grid (NW10). Both are individual sites, not a London-wide position.
- Planned investment
- Flexibility procurement is the approved route at both sites. No investment figure is published in the source document.
- Flexible connections
- UK Power Networks reports procuring flexibility at both Bow and Willesden Grid, with 90% of the 2026/27 Bow requirement recorded as procured.
Slough and the Thames Valley
○Insufficient evidenceEvidence collection has begun for Slough and the Thames Valley but no pressure rating can be published. The published methodology does not yet define what separates Low, Moderate, High and Severe pressure, and both current evidence records come from a single SSEN consultation draft covering the Iver 132kV grid supply point area rather than Slough alone.
- Connection demand
- SSEN states that over 600 MVA of data centres are already connected and contracted with capacity across the Iver 132kV grid supply point, with the majority of that load coming from the Slough area. The figure covers the whole grid supply point area, combines connected with contracted capacity, and is stated in MVA.
- Known delays
- No published average connection waiting time for this area has been established.
- Network constraints
- Both 132/33kV transformers feeding Chalvey bulk supply point are forecast to overload under an N-1 condition, in a year varying between 2030 and 2041 depending on the scenario applied.
- Planned investment
- Reinforcement options are identified — a third 132/33kV transformer and a 132kV circuit from the proposed Langley Hall switching station — but no funding, cost or delivery date is published, and identifying an option does not guarantee a connection date.
- Flexible connections
- No flexible-connection information for this area has been established.
South East England
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
Midlands
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
North West England
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
North East and Yorkshire
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
Scotland
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
Wales
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —
Northern Ireland
○Insufficient evidenceNo rating has been assigned. Data not yet available.
- Connection demand
- —
- Known delays
- —
- Network constraints
- —
- Planned investment
- —
- Flexible connections
- —
Confidence: —Last reviewed: —