Back to the tracker

Cambois data centre campus

QTS (Blackstone)

Cambois, North EastUnder construction Verified

Outline planning permission, with all matters reserved, granted by Northumberland County Council on 8 May 2025 for up to ten Class B8 data centre buildings totalling up to 540,000 sqm gross internal area, plus a substation, emergency generators and ancillary structures. The council committee report states approximately 72 MW of IT capacity per building, about 720 MW across the full campus; this is recorded as IT load. Initial earthworks began in October 2025 and reserved matters for phase 1 were approved in December 2025, so the project is recorded as under construction.

Key facts

Operator / developer
QTS (Blackstone)
Location
Land at former power station site on the northern side of Cambois, Northumberland, Cambois, North East, United Kingdom
Status
Under construction
Facility type
Data centre
AI relevance
Not stated
Floor area
540,000 m²
Construction jobs
1,200
Permanent jobs
400

Power & grid

Published capacity
  • 720 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
Share of UK tracked capacity
20% of published it load
Network operator
SSE (on-site substation); National Grid
Grid position
About 1,100MW operational power requirement; on-site SSE substation connecting to a National Grid substation south of the site (committee report)
Power
The approved outline scheme comprises up to ten data centre buildings, each stated in the council committee report as providing approximately 72 MW of IT capacity, giving approximately 720 MW of IT capacity across the full campus. The report also records 580 standby generators across the campus (1 x 1.25 MWe and 57 x 2.4 MWe per building). No grid connection capacity is published.
Backup generation
1,380.5 MW
Backup fuel
Diesel
On-site generation
580 diesel standby generators (58 per building across 10 buildings: 1 x 1.25MWe + 57 x 2.4MWe each), fitted with SCR; about 2 hours of testing per generator per year. MW total is calculated from the configuration in the committee report.
Heat reuse
Space to be designed in for a future district heating connection; developer welcomes talks with local partners.

Planning

Planning route
Local planning (TCPA)
Planning reference
24/04112/OUTES
Planning decision
Application permitted (outline, all matters reserved)
Decision date
8 May 2025
Green belt
No
Land area
102.3 ha
Recorded objections
2
Recorded support
6

Benefits vs drawbacks

Benefits

  • About 1,200 construction jobs and about 400 permanent jobs, plus about 2,700 indirect jobs at full operationSource
  • Regenerates a 102ha brownfield former power station coal yard, vacant for 20+ yearsSource
  • Water-free cooling using air-cooled chillersSource

Drawbacks

  • Operational emissions of about 184,160 tCO2e a year at full operation, about 8% of Northumberland's baseline (moderate adverse)Source
  • 580 diesel standby generatorsSource
  • Significant adverse visual effects remain despite height reductionsSource

S106: £40,000 for a wader mitigation site; education, employment and training plan; local supplier strategy; local recruitment within 25 miles prioritised.

Timeline

  1. Northumberland County Council permitted the outline application (24/04112/OUTES).

    Source

Reality Score

53Possible
How we score
Planning18/25
Grid connection0/25
Land and funding20/20
Delivery team15/15
Momentum0/15

Sources

Last verified

27 September 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.