Cambois data centre campus
QTS (Blackstone)
Outline planning permission, with all matters reserved, granted by Northumberland County Council on 8 May 2025 for up to ten Class B8 data centre buildings totalling up to 540,000 sqm gross internal area, plus a substation, emergency generators and ancillary structures. The council committee report states approximately 72 MW of IT capacity per building, about 720 MW across the full campus; this is recorded as IT load. Initial earthworks began in October 2025 and reserved matters for phase 1 were approved in December 2025, so the project is recorded as under construction.
Who is delivering the project?
- Developer and operator
- QTS (Blackstone) is the developer and operator. Renaissance Land Limited is the planning applicant and is named alongside QTS on the planning submissions.Quod for Renaissance Land Limited (application document, on a mirror)
- Environmental consultant
- Arcadis prepares assessments for QTS. Its Habitats Regulations Assessment in the August 2025 phase 1 reserved matters submission is dated 15 August 2025 and states it was prepared for QTS, as does its May 2026 Ecological Impact Assessment for enabling works phase B. This is a consultancy appointment, not a construction contract.Arcadis for QTS: Habitats Regulations Assessment, August 2025 (on a mirror) Arcadis for QTS: Ecological Impact Assessment, May 2026 (on a mirror)
- Enabling works
- Initial earthworks began in October 2025. Ridge and Partners says it is Principal Designer for the enabling works, a design safety role rather than a building contract. Rainton Construction Limited applied to the Environment Agency (notice published 10 February 2026) for a permit to permanently deposit waste already on the site; the notice does not state its contract role.BBC News Ridge and Partners Environment Agency (GOV.UK)
- Foundations
- Keller says it holds a subcontract for ground improvement (vibro stone columns) and CFA piling for data centres 1 and 2 and the guard house; on 6 August 2026 it said this work was expected to finish later that month. Keller does not name the firm it is contracted to.Keller UK (primary, contractor)
- Main contractor
- No main contractor for the data centre buildings has been named in the sources recorded here.
- Contracts awarded
- The only publicly documented delivery appointments are Ridge (Principal Designer, enabling works) and Keller (ground engineering subcontract). No contract values have been published.
Summary checked against this record on 21 November 2026. If anything differs, the detailed record and sources below take precedence. See the UK data centre map.
Reality Score
A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.
Good evidence on several factors. Check for a named design or delivery team before planning an approach.
Supplying this project? Pro tells you every Monday when it moves →Key facts
- Operator / developer
- QTS (Blackstone)
- Location
- Land at former power station site on the northern side of Cambois, Northumberland, Cambois, North East, United Kingdom
- Status
- Under construction
- Facility type
- Data centre
- AI relevance
- Not stated
- Floor area
- 540,000 m²
- Construction jobs
- 1,200
- Permanent jobs
- 400
Power & grid
- Published capacity
- 720 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
- Share of UK tracked capacity
- 14.9% of published it load
- Network operator
- SSE (on-site substation); National Grid
- Grid position
- About 1,100MW operational power requirement; on-site SSE substation connecting to a National Grid substation south of the site (committee report)
- Power
- The approved outline scheme comprises up to ten data centre buildings, each stated in the council committee report as providing approximately 72 MW of IT capacity, giving approximately 720 MW of IT capacity across the full campus. The report also records 580 standby generators across the campus (1 x 1.25 MWe and 57 x 2.4 MWe per building). No grid connection capacity is published.
- Backup generation
- 1,380.5 MW
- Backup fuel
- Diesel
- On-site generation
- 580 diesel standby generators (58 per building across 10 buildings: 1 x 1.25MWe + 57 x 2.4MWe each), fitted with SCR; about 2 hours of testing per generator per year. MW total is calculated from the configuration in the committee report.
- Heat reuse
- Space to be designed in for a future district heating connection; developer welcomes talks with local partners.
Planning
- Planning route
- Local planning (TCPA)
- Planning reference
- 24/04112/OUTES
- Planning decision
- Application permitted (outline, all matters reserved)
- Decision date
- 8 May 2025
- Green belt
- No
- Land area
- 102.3 ha
- Recorded objections
- 2
- Recorded support
- 6
Benefits vs drawbacks
Benefits
S106: £40,000 for a wader mitigation site; education, employment and training plan; local supplier strategy; local recruitment within 25 miles prioritised.
Timeline
Northumberland County Council permitted the outline application (24/04112/OUTES).
SourceReserved matters permission 25/02911/REM issued for phase 1 (data centres 1 and 2).
SourceQuod, for Renaissance Land and QTS, applied for non-material amendments to the approved plans in the phase 1 reserved matters permission.
Source
Sources
- Planning application 24/04112/OUTES - Outline application for up to ten data centre buildings, former power station site, Cambois
Primary record · Northumberland County Council · 2025-05-08 · accessed 2026-08-12
- Strategic Planning Committee report, application 24/04112/OUTES, Land at former power station site, Cambois
Secondary source · Northumberland County Council · 2025-03-04
- Enabling works now underway for £10 billion QTS data centre campus in Northumberland
Secondary source · Ridge and Partners · 2025-11-12
- First phase of Blyth data centre construction approved
Secondary source · BBC News · 2025-12-02
- Keller lays foundations for huge data centre
Secondary source · Keller UK (primary, contractor) · 2026-08-06
- S96A non-material amendment covering letter citing reserved matters permission 25/02911/REM dated 8 January 2026
Secondary source · Quod for Renaissance Land and QTS (application document, on a mirror) · 2026-10-23
- Reserved matters covering letter naming Renaissance Land Limited as applicant and QTS as developer and operator
Secondary source · Quod for Renaissance Land Limited (application document, on a mirror) · 2025-05-21
- Reserved Matters Application Phase 1: Habitats Regulations Assessment, prepared for QTS by Arcadis
Secondary source · Arcadis for QTS: Habitats Regulations Assessment, August 2025 (on a mirror) · 2025-08-15
- Enabling Works Phase B: Ecological Impact Assessment, prepared for QTS by Arcadis
Secondary source · Arcadis for QTS: Ecological Impact Assessment, May 2026 (on a mirror) · 2026-05-08
- Rainton Construction Limited: environmental permit application advertisement EPR/JP3321LF/A001 (Project Wind, QTS Data Centres, Cambois)
Secondary source · Environment Agency (GOV.UK) · 2026-02-10
Last verified
11 November 2026