Cambois data centre campus

QTS (Blackstone)

Cambois, North EastUnder construction Verified

Outline planning permission, with all matters reserved, granted by Northumberland County Council on 8 May 2025 for up to ten Class B8 data centre buildings totalling up to 540,000 sqm gross internal area, plus a substation, emergency generators and ancillary structures. The council committee report states approximately 72 MW of IT capacity per building, about 720 MW across the full campus; this is recorded as IT load. Initial earthworks began in October 2025 and reserved matters for phase 1 were approved in December 2025, so the project is recorded as under construction.

Who is delivering the project?

Developer and operator
QTS (Blackstone) is the developer and operator. Renaissance Land Limited is the planning applicant and is named alongside QTS on the planning submissions.Quod for Renaissance Land Limited (application document, on a mirror)
Environmental consultant
Arcadis prepares assessments for QTS. Its Habitats Regulations Assessment in the August 2025 phase 1 reserved matters submission is dated 15 August 2025 and states it was prepared for QTS, as does its May 2026 Ecological Impact Assessment for enabling works phase B. This is a consultancy appointment, not a construction contract.Arcadis for QTS: Habitats Regulations Assessment, August 2025 (on a mirror) Arcadis for QTS: Ecological Impact Assessment, May 2026 (on a mirror)
Enabling works
Initial earthworks began in October 2025. Ridge and Partners says it is Principal Designer for the enabling works, a design safety role rather than a building contract. Rainton Construction Limited applied to the Environment Agency (notice published 10 February 2026) for a permit to permanently deposit waste already on the site; the notice does not state its contract role.BBC News Ridge and Partners Environment Agency (GOV.UK)
Foundations
Keller says it holds a subcontract for ground improvement (vibro stone columns) and CFA piling for data centres 1 and 2 and the guard house; on 6 August 2026 it said this work was expected to finish later that month. Keller does not name the firm it is contracted to.Keller UK (primary, contractor)
Main contractor
No main contractor for the data centre buildings has been named in the sources recorded here.
Contracts awarded
The only publicly documented delivery appointments are Ridge (Principal Designer, enabling works) and Keller (ground engineering subcontract). No contract values have been published.

Summary checked against this record on 21 November 2026. If anything differs, the detailed record and sources below take precedence. See the UK data centre map.

Reality Score

67LikelyStatus: Under construction
How we score
Planning25/25
Grid connection0/25
Land and funding20/20
Delivery team15/15
Momentum7/15

A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.

Good evidence on several factors. Check for a named design or delivery team before planning an approach.

Supplying this project? Pro tells you every Monday when it moves →

Key facts

Operator / developer
QTS (Blackstone)
Location
Land at former power station site on the northern side of Cambois, Northumberland, Cambois, North East, United Kingdom
Status
Under construction
Facility type
Data centre
AI relevance
Not stated
Floor area
540,000 m²
Construction jobs
1,200
Permanent jobs
400

Power & grid

Published capacity
  • 720 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
Share of UK tracked capacity
14.9% of published it load
Network operator
SSE (on-site substation); National Grid
Grid position
About 1,100MW operational power requirement; on-site SSE substation connecting to a National Grid substation south of the site (committee report)
Power
The approved outline scheme comprises up to ten data centre buildings, each stated in the council committee report as providing approximately 72 MW of IT capacity, giving approximately 720 MW of IT capacity across the full campus. The report also records 580 standby generators across the campus (1 x 1.25 MWe and 57 x 2.4 MWe per building). No grid connection capacity is published.
Backup generation
1,380.5 MW
Backup fuel
Diesel
On-site generation
580 diesel standby generators (58 per building across 10 buildings: 1 x 1.25MWe + 57 x 2.4MWe each), fitted with SCR; about 2 hours of testing per generator per year. MW total is calculated from the configuration in the committee report.
Heat reuse
Space to be designed in for a future district heating connection; developer welcomes talks with local partners.

Planning

Planning route
Local planning (TCPA)
Planning reference
24/04112/OUTES
Planning decision
Application permitted (outline, all matters reserved)
Decision date
8 May 2025
Green belt
No
Land area
102.3 ha
Recorded objections
2
Recorded support
6

Benefits vs drawbacks

Benefits

  • About 1,200 construction jobs and about 400 permanent jobs, plus about 2,700 indirect jobs at full operationSource
  • Regenerates a 102ha brownfield former power station coal yard, vacant for 20+ yearsSource
  • Water-free cooling using air-cooled chillersSource

Drawbacks

  • Operational emissions of about 184,160 tCO2e a year at full operation, about 8% of Northumberland's baseline (moderate adverse)Source
  • 580 diesel standby generatorsSource
  • Significant adverse visual effects remain despite height reductionsSource

S106: £40,000 for a wader mitigation site; education, employment and training plan; local supplier strategy; local recruitment within 25 miles prioritised.

Timeline

  1. Northumberland County Council permitted the outline application (24/04112/OUTES).

    Source
  2. Reserved matters permission 25/02911/REM issued for phase 1 (data centres 1 and 2).

    Source
  3. Quod, for Renaissance Land and QTS, applied for non-material amendments to the approved plans in the phase 1 reserved matters permission.