Amazon Data Services, Ridgeway Distribution Centre, Iver

Amazon Web Services

Iver, South EastApproved

Buckinghamshire Council approved Amazon Data Services UK's plans on 28 September 2026 to replace 17 industrial and warehouse units at the Ridgeway Distribution Centre, Iver, with a single two-storey data centre (about 30,525 sqm, main building about 20m high), a substation compound and a yard for 27 backup generators on a 7.3ha site. No MW figure has been published. The site is outside the green belt but in the Colne Valley Regional Park setting and an air quality management area. The Environment Agency generator permit is still to be decided.

Key facts

Operator / developer
Amazon Web Services
Location
Ridgeway Distribution Centre (Ridgeway Trading Estate), Iver, SL0 9JQ, South East, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
Not stated
Announced
28 October 2025
Floor area
30,525 m²
Permanent jobs
60

Power & grid

Power
No IT load or grid capacity published. Scheme includes an on-site substation compound with two switchrooms.
Backup fuel
Mixed
On-site generation
27 backup generators, primarily HVO with diesel as backup; testing limited to 7:30am–6pm weekdays and 8am–1pm Saturdays. Environment Agency permit application EPR/TP3621MM/A001 (advertised 13 Aug 2026) not yet determined.
Cooling
Direct evaporative cooling with outside air for most of the year; adiabatic cooling using rainwater as primary supply in warmer periods (DCD).

Planning

Planning route
Local planning (TCPA)
Planning reference
T3PLZVESLZY00
Planning decision
Approved subject to conditions and a legal agreement
Decision date
28 September 2026
Green belt
No
Land area
7.3 ha

Benefits vs drawbacks

Benefits

  • Up to 60 full-time jobs on siteSource
  • Substantially fewer goods vehicle movements than the previous warehouse useSource
  • £600,382 for air-quality offsetting and £73,000 for rights of waySource
  • Reuses previously developed industrial land, outside the green beltSource

Drawbacks

  • Planners accepted some harm to the landscape and the Colne Valley Regional ParkSource
  • 27 backup generators in an air quality management areaSource
  • Ivers Parish Council raised traffic and air-quality concernsSource
  • No computing or grid capacity disclosedSource

£600,382 towards air-quality offset projects and £73,000 for public rights of way improvements, secured by legal agreement; generator emissions monitoring required.

Timeline

  1. Amazon Data Services UK files plans to replace 17 warehouse units with a data centre (ref T3PLZVESLZY00).

    Source
  2. Environment Agency advertises generator permit application EPR/TP3621MM/A001.

    Source
  3. Buckinghamshire Council approves the scheme subject to conditions and a legal agreement.

    Source

Sources

Last verified

30 September 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.