Thames Valley Park Data Centre, Earley

Earley, South EastProposed

Property investor Mapeley has applied to Wokingham Borough Council for outline permission to replace three office buildings on the Microsoft campus at Thames Valley Park, Earley, with a data centre of 72MW IT load and about 37,000 sqm. Peak demand would be about 110MW, but only 1.8MW of grid supply is available now, so the first phase would run on gas-fed fuel cells until a larger grid connection arrives, expected around 2037. Demolition is planned for 2027 and the first data halls for 2030, with a decision expected by March 2027. The scheme is put at more than £200m. Microsoft is not involved in the proposal and its lease is reported to end in December 2027. A petition against the scheme has several thousand signatures. No operator or tenant is named.

Key facts

Operator / developer
Mapeley
Location
Microsoft Campus, Thames Valley Park, Earley, RG6 1WG, South East, United Kingdom
Status
Proposed
Facility type
Data centre
AI relevance
Not stated
Floor area
37,000 m²
Stated investment
£200,000,000
Construction jobs
245

Power & grid

Published capacity
  • 72 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
  • 110 MW — Published electrical demandThe total electrical demand stated for the site, including cooling and losses.
Share of UK tracked capacity
2% of published it load
Network operator
Scottish and Southern Electricity Networks (SSEN)
Grid position
60MVA connection secured from SSEN; available from 2037 after transmission reinforcement
Grid connection
The applicant's Utilities Statement (September 2026) says a 60MVA connection has been secured from SSEN and that National Grid Transmission has confirmed it will be available from 2037, delivered at 33kV from Reading primary substation by directional drilling under the railway. Until then the site would run on solid oxide fuel cells with a stated capacity of 49.9MW, supplied from a new connection to the high-pressure gas main. The Energy Strategy gives 42.5MW for the fuel cells.
Power
72MW of IT load, with peak demand of about 110MW once cooling and electrical plant are included. The first phase would run on gas-fed fuel cells until the grid connection arrives; a second phase of about 40MW would follow it.
On-site generation
Gas-fed solid-oxide fuel cells would power the first phase from about 2028 to 2037: 49.9MW installed, giving about 42.5MW of effective supply (reported from the application). The developer describes them as able to move to biomethane or hydrogen later. Separate generators are proposed for emergency backup.
Heat reuse
Waste heat could be exported to a district heat network (reported from the application).

Planning

Planning route
Local planning (TCPA)
Planning reference
262274
Planning decision
Outline application submitted in late September 2026; decision expected by March 2027
Land area
5.3 ha

Benefits vs drawbacks

Benefits

  • More than £200m of construction investment (developer figure)Source
  • Up to 245 construction jobs; the application is reported as supporting 40 to 65 operational jobs (the project website earlier cited at least 115)Source
  • Reuses an existing office campus rather than undeveloped landSource
  • Biodiversity net gain of 22.69% and possible heat export to a district heat networkSource

Drawbacks

  • Would run on gas-fed fuel cells until about 2037 because only 1.8MW of grid supply is available nowSource
  • The application's environmental assessment is reported as finding significant adverse effects on greenhouse gas emissionsSource
  • Data halls up to about 100ft (30m) highSource
  • A petition against the scheme has several thousand signatures, and residents and a local councillor have objectedSource
  • No operator or tenant is namedSource

Timeline

  1. Public consultation event held at Pearson Hall, Sonning.

    Source
  2. Outline application for a 72MW data centre reported as submitted to Wokingham Borough Council in late September 2026 (exact lodging date not confirmed). A decision is expected by March 2027.

    Source

Reality Score

33Speculative
How we score
Planning8/25
Grid connection0/25
Land and funding10/20
Delivery team8/15
Momentum7/15

Sources

Last verified

7 October 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.