Era4 AI data centre, Erin Landfill, Chesterfield

Era4 (formerly Carbon3.ai)

Chesterfield (Duckmanton / Poolsbrook), East MidlandsOperational

Era4 runs a modular AI data centre of HPE AI Mod Pods on the Erin Landfill site off Erin Road near the M1, outside Chesterfield. It is powered mainly by landfill gas generated on site, with the grid as backup. Fireworks has contracted the whole site, 5MW of liquid-cooled Nvidia B300 capacity, under a multi-year deal announced in October 2026.

Reality Score

92Building
How we score
Planning25/25
Grid connection25/25
Land and funding20/20
Delivery team15/15
Momentum7/15

Packages are being let now.

Supplying this project? See the Market Entry Sprint →

Key facts

Operator / developer
Era4 (formerly Carbon3.ai)
Location
Chesterfield (Duckmanton / Poolsbrook), East Midlands, United Kingdom
Status
Operational
Facility type
Data centre
AI relevance
stated

Planning

Planning route
Local planning (TCPA)
Planning decision
Planning permission granted Nov 2025 for up to five modular data centre units

Sources

Last verified

5 November 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.