Microsoft Newport Imperial Park (CWL01), former Quinn Radiators site

Microsoft

Newport, WalesApproved

Microsoft's datacentre on the former Quinn Radiators factory site at Celtic Way, Imperial Park, Newport (application 24/0006). Newport City Council's planning committee unanimously approved demolition of the remaining buildings and two data centre buildings with diesel backup generators on 3 July 2024; Microsoft agreed a £104,000 walking and cycling contribution. Senedd Research (July 2026) puts the planned site at around 200 MW IT load; the planning papers give no MW figure. The site is separate from the Vantage (former NGD) campus at Imperial Park.

Key facts

Operator / developer
Microsoft
Location
Former Quinn Radiators site, Celtic Way, Imperial Park, Newport, Newport, Wales, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
Not stated

Power & grid

Published capacity
  • 200 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
Share of UK tracked capacity
19.5% of published it load
Backup fuel
Diesel

Planning

Planning route
Local planning (TCPA)
Planning reference
24/0006
Planning decision
Approved
Decision date
3 July 2024

Benefits vs drawbacks

Benefits

  • About 120 jobs reported at approvalSource
  • Reuses the former Quinn Radiators factory site (brownfield), closed in 2019Source
  • £104,000 contribution towards walking and cycling routes along Celtic WaySource
  • Around 200 MW of IT load planned, adding AI and cloud capacity in WalesSource

Drawbacks

  • Diesel backup generators with 14 m chimneys; a councillor asked for a report on pollution during power emergencies, and approval went ahead without itSource

Timeline

  1. Microsoft confirmed plans for a datacentre on the former Quinn Radiators site at Imperial Park and began pre-application consultation.

    Source
  2. Newport City Council's planning committee unanimously approved application 24/0006: demolition of the remaining Quinn Radiators buildings and two data centre buildings with backup generators.

    Source
  3. Reported: Microsoft to fund £104,000 of walking and cycling routes on Celtic Way under the planning agreement for the data centre.

    Source

Sources

Last verified

29 September 2026

Email me when this changes