Devon Data Campus (Xlinks), near Great Torrington

Xlinks

Great Torrington, South WestProposed

Xlinks proposes a campus of up to 1.5GW of AI data centre capacity plus a 1.8GW battery storage facility on about 344ha of farmland near Great Torrington in the North Devon UNESCO biosphere reserve, with an estimated £12.2–13.8bn investment. Two applications to Torridge District Council are expected; none has been submitted. Public consultation has been postponed amid strong local opposition. Xlinks says some reported details, such as a drought water-use figure, reflect an outdated design.

Key facts

Operator / developer
Xlinks
Location
Between Great Torrington, Huntshaw and Weare Giffard (Alverdiscott area), North Devon, Great Torrington, South West, United Kingdom
Status
Proposed
Facility type
Data centre
AI relevance
High — AI/compute led
Stated investment
£13,800,000,000

Power & grid

Published capacity
  • 1,500 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
Share of UK tracked capacity
59.4% of published it load
Power
Up to 1.5GW of AI-optimised compute capacity (Xlinks); CPRE Devon reports 1.5GW IT load and 1.8GW peak site load. Battery storage 1.8GW is not data centre load.
On-site generation
Separate 1.8GW battery energy storage application planned alongside the data centre (about 96 acres, per CPRE Devon).

Planning

Planning route
Local planning (TCPA)
Land area
344 ha

Benefits vs drawbacks

Benefits

  • £12.2–13.8bn capital investment; 2,000–3,500 construction jobs and 600–1,200 permanent roles (developer estimates)Source
  • Would be one of the largest AI compute sites in the UKSource

Drawbacks

  • About 344ha of farmland inside the North Devon UNESCO biosphere reserveSource
  • Five buildings up to 40m high and a 96-acre battery facility in open countrysideSource
  • Early design documents suggested up to 2.9bn litres of water a year in severe drought; Xlinks says this is outdatedSource
  • Developer has not built a data centre before; petition of 36,000+ signatures for a pause outside AI Growth ZonesSource

Xlinks promises community benefit packages, skills/STEAM programmes and local supply chain commitments.

Timeline

  1. Public consultation postponed amid growing local opposition; no application submitted yet.

    Source

Sources

Last verified

30 September 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.