Back to the tracker

Deep Green Bradford, Listerhills Road

Deep Green Technologies

Bradford, Yorkshire and the HumberApprovedData centreCapacity not published Verified — 1 source on file

Consent reported May 2026, with heat reuse into the Bradford Energy Centre. A 5.6 MW figure is reported without a stated definition.

Project detail

Operator / developer
Deep Green Technologies
Location
Bradford, Yorkshire and the Humber, United Kingdom
Status
Approved
AI relevance
Not stated
Announced
Not published
Target live date
Not published
Published capacity
Not published. No capacity figure means none has been published — it does not mean zero.
Floor area
Not published
Stated investment
Not published
Power
No capacity figure appears on the City of Bradford MDC register entry. Press reporting cites 5 MW as filed and 5.6 MW as approved; neither publisher states whether that is IT load, grid connection or total electrical demand, so no figure is recorded here.
Grid connection
Not published
Cooling
Not published
Water
Not published
Planning authority
City of Bradford Metropolitan District Council
Planning reference
25/02212/MAF
Planning decision
Grant subject to Unilateral Undertaking
Decision date
2026-05-13
Construction start
Not published
Expected completion
Not published
Operational since
Not published
Confidence
High confidence
Last verified
2026-08-19

Sources

Entry last updated 19/08/2026. Spotted something wrong? Tell us.

Yorkshire and the Humber in context