Back to the tracker
Deep Green Bradford, Listerhills Road
Deep Green Technologies
Bradford, Yorkshire and the HumberApprovedData centreCapacity not published Verified — 1 source on file
Consent reported May 2026, with heat reuse into the Bradford Energy Centre. A 5.6 MW figure is reported without a stated definition.
Project detail
- Operator / developer
- Deep Green Technologies
- Location
- Bradford, Yorkshire and the Humber, United Kingdom
- Status
- Approved
- AI relevance
- Not stated
- Announced
- Not published
- Target live date
- Not published
- Published capacity
- Not published. No capacity figure means none has been published — it does not mean zero.
- Floor area
- Not published
- Stated investment
- Not published
- Power
- No capacity figure appears on the City of Bradford MDC register entry. Press reporting cites 5 MW as filed and 5.6 MW as approved; neither publisher states whether that is IT load, grid connection or total electrical demand, so no figure is recorded here.
- Grid connection
- Not published
- Cooling
- Not published
- Water
- Not published
- Planning authority
- City of Bradford Metropolitan District Council
- Planning reference
- 25/02212/MAF
- Planning decision
- Grant subject to Unilateral Undertaking
- Decision date
- 2026-05-13
- Construction start
- Not published
- Expected completion
- Not published
- Operational since
- Not published
- Confidence
- High confidence
- Last verified
- 2026-08-19
Sources
- Planning application 25/02212/MAF — Construction of data centre and associated infrastructure, Land to the East of Bradford Energy Centre, Listerhills Road
Primary record · City of Bradford Metropolitan District Council · 2026-05-13
Entry last updated 19/08/2026. Spotted something wrong? Tell us.
Yorkshire and the Humber in context
See every tracked project in Yorkshire and the Humber, the capacity that has been disclosed there and how it connects to wider UK demand.