Nscale Loughton sovereign AI data centre
Nscale
Nscale's Loughton, Essex site was named in the government's 2025 AI strategy as the UK's largest sovereign AI supercomputer and was due to open in 2027. Planning permission is in place, but the Guardian reported on 24 September 2026 that UK Power Networks had told Nscale it cannot supply the requested 90MW until the early-to-mid 2030s. In October 2026 Microsoft, the anchor tenant, ended its agreement for the site; Microsoft said the decision relates to this single site. Nscale says it remains committed to Loughton and is looking at alternative power sources.
Loughton data centre at a glance
- Location
- A former scaffolding yard in Loughton, Essex, in the Epping Forest District Council area. Nscale is the developer and operator.
- Planning
- Approved. Outline planning permission was granted in 2024 and a revised scheme was approved in mid-2026.Capacity
- Grid power
- Nscale requested up to 90 MW from UK Power Networks. The Guardian reported on 24 September 2026 that UK Power Networks cannot supply that power until the early-to-mid 2030s; UK Power Networks has not confirmed this.The Guardian (via inkl)
- Timeline
- Named in the government's 2025 AI strategy, the site was originally due to open in 2027. In October 2026 Microsoft, the anchor tenant, ended its agreement for this site. Nscale says it remains committed to Loughton and is looking at alternative power sources.Reuters (secondary)
Summary checked against this record on 7 November 2026. If anything differs, the detailed record and sources below take precedence. See the UK data centre map.
Reality Score
A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.
Public evidence for this project is limited so far. Projects in the UK with a higher score (Strong evidence or Likely):
- Pure DC LON01 B2, Brent Cross · Strong evidence · Under construction
- Era4 AI data centre, Erin Landfill, Chesterfield · Strong evidence · Operational
- GreenScale Derry Campus (formerly Atlantic Hub), Foyle Port · Strong evidence · Approved
Key facts
- Operator / developer
- Nscale
- Location
- Loughton (former scaffolding yard), Loughton, East of England, United Kingdom
- Status
- Approved
- Facility type
- Data centre
- AI relevance
- High — AI/compute led
Power & grid
- Network operator
- UK Power Networks
- Grid position
- Reported: power not available until early-to-mid 2030s
- Grid connection
- Up to 90MW requested from UK Power Networks
- Power
- Nscale has requested up to 90MW. UK Power Networks has reportedly said sufficient power cannot be supplied until the early-to-mid 2030s (Guardian, 24 Sep 2026; not confirmed by UKPN).
- On-site generation
- Nscale is exploring on-site generation, including gas fuel cells, as an interim measure (Guardian).
Planning
- Planning route
- Local planning (TCPA)
- Planning decision
- Permission granted (outline 2024; revised scheme approved mid-2026)
Benefits vs drawbacks
Benefits
Timeline
Guardian reports UK Power Networks cannot supply the requested 90MW until the early-to-mid 2030s; 2027 launch expected to slip.
SourceMicrosoft ends its agreement to anchor the Loughton site after grid power slipped into the 2030s. Nscale says it is still committed and is looking at alternative power sources.
Source
Sources
- Launch of UK's largest AI supercomputer delayed by power supply problems
Secondary source · The Guardian (via inkl) · 24 September 2026
- UK government reportedly urged Nscale AI data centre approval
Secondary source · Capacity
- Nscale latest to face public backlash over proposed data centre
Secondary source · Data Centre Review · 30 March 2026
- Nscale Loughton datacentre grid power delay
Secondary source · runtimewire.com (secondary)
- Microsoft pulls out of Nscale deal for UK's largest AI data centre
Secondary source · City AM (secondary) · 2026-10-19
- Microsoft pulls out of Nscale deal, putting $35bn IPO at risk
Secondary source · Computing (secondary) · 2026-10-19
- Microsoft pulls out of UK Nscale data centre deal over power delay
Secondary source · Reuters (secondary) · 2026-10-19
Last verified