Data Centre Campus, Ampthill Road, Bedford

Bedford, East of EnglandProposed Verified

On 15 June 2026 the Secretary of State issued a direction under section 35 of the Planning Act 2008 requiring this proposed data centre campus at Ampthill Road, Bedford, in Central Bedfordshire, to be consented through a Development Consent Order. This is a designation at the pre-application stage: no application has been examined or decided, and no power capacity figure is published in the direction or decision letter.

Reality Score

17Headline onlyStatus: Proposed
How we score
Planning0/25
Grid connection0/25
Land and funding10/20
Delivery team0/15
Momentum7/15

A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.

Public evidence for this project is limited so far. Projects in the UK with a higher score (Strong evidence or Likely):

Request a sample report on higher-scoring projects →

Key facts

Operator / developer
Questpit Limited
Location
Bedford, East of England, United Kingdom
Status
Proposed
Facility type
Data centre
AI relevance
Not stated

Power & grid

Power
No capacity figure is published in the Section 35 direction or decision letter. The developer's own marketing describes a 143-acre campus with "power secured through a grid connection and on-site generation" but states no MW or MVA figure, so nothing is recorded.

Planning

Planning route
DCO / NSIP
Planning reference
PCU/NSIP/P0240/3378443 (Section 35 direction)
Planning decision
Section 35 direction granted: treated as nationally significant infrastructure requiring a Development Consent Order

Benefits vs drawbacks

Benefits

  • Going through the national infrastructure (DCO) route, with full examination of environment, transport, utilities and community impactSource

Drawbacks

  • No capacity, site area or jobs figures publishedSource
  • The DCO process is long; no application has been submitted yetSource

Timeline

  1. Section 35 direction granted: the scheme is to be treated as nationally significant infrastructure needing a Development Consent Order.

    Source

Sources

Last verified

15 November 2026