CX Technology Campus, Chapelcross

Annan, ScotlandProposed

CX Tech has applied to Dumfries and Galloway Council for planning permission in principle for a campus of eight data centres on about 57ha of land north of the former Chapelcross nuclear power station, near Annan. It is reported at 1GW and £16.5bn, with up to 162,000 sqm of data-centre floorspace in buildings up to 40m high, built in phases from 2027 to 2035. The Scottish Government has paused decisions on large data centres until the end of 2026, and local campaigners and APRS oppose the scheme. No operator or tenant is named.

Key facts

Operator / developer
CX Tech Limited
Location
Land north of the former Chapelcross nuclear power station, near Annan, Annan, Scotland, United Kingdom
Status
Proposed
Facility type
Data centre
AI relevance
Not stated
Floor area
162,000 m²
Stated investment
£16,500,000,000
Construction jobs
750
Permanent jobs
540

Power & grid

Published capacity
  • 1,000 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
Grid position
Grid connection application status not published
Grid connection
132kV infrastructure is present at the site; SP Energy Networks refurbished the 14.23km Gretna to Chapelcross line in August 2026. No grid connection agreement for the campus has been published.
Power
Reported as a 1GW campus of eight data centres. Sources do not say whether this is IT load or total demand, and the developer's pre-application notice gives no power figure. Campaigners estimate annual demand of about 7 million MWh.
On-site generation
Developer is exploring private-wire links to nearby wind, solar and biomass generation and possible energy storage; it cites 1GW of renewable generation within 5km and 2GW within 20km.
Water
Developer says each building would use about as much water as four homes a year.
Cooling
Closed-loop, non-evaporative air cooling; target PUE of 1.30 or better (trade press reporting of the developer's plans).
PUE target
1.3

Planning

Planning route
Scottish PPiP
Land area
57 ha

Benefits vs drawbacks

Benefits

  • About £16.5bn investment (developer figure)Source
  • About 750 construction jobs over eight years and about 540 permanent roles (developer figures; some reports say 450)Source
  • Next to a former nuclear site with existing 132kV grid infrastructure and nearby renewable generationSource
  • Closed-loop air cooling with low water use and a target PUE of 1.30Source

Drawbacks

  • At 1GW it would exceed any data centre now operating; campaigners put demand at about 7 million MWh a yearSource
  • Local petition of about 1,000 signatures; APRS and campaigners cite loss of farmland and woodland, emissions and landscape impactSource
  • Scottish Government has paused data-centre decisions until the end of 2026Source
  • No operator, tenant or grid connection agreement publishedSource

About 40 apprenticeships a year during construction and an on-site training centre; the developer refers to a Community Wealth Building approach.

Timeline

  1. Pre-application consultation began, with events at Creca Village Hall and Victoria Hall, Annan on 12 to 13 May and 16 to 17 June 2026.

    Source
  2. Application for planning permission in principle reported as submitted to Dumfries and Galloway Council (exact lodging date not confirmed).

    Source

Sources

Last verified

2 October 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.