Kao Data Kenwood Point, Stockport

Kao Data

Stockport, North WestApproved Verified

Demolition of an existing industrial and warehouse building and erection of a 25,900 sq m data centre at Kenwood Point, Stockport, with associated parking, servicing and access. Approved by Stockport Council's Heatons and Reddish Area Committee. Applicant recorded as KD 5 Limited. Kao Data's written evidence to Parliament (IGR0029, 13 January 2025) identifies 40 MW of IT capacity. This is recorded as published IT load and included in comparable IT-capacity totals; it is not a verified grid-connection capacity. Programme update checked 8 October 2026: Kao Data's dated statement of 1 July 2026 says demolition is complete and the site has been prepared; substation and power-cabling works were ongoing. Main data-centre buildings are expected to be constructed in 2027, with power anticipated in late 2027 and operation in 2028. These are operator targets, not confirmed completion dates. The older location page still gives Q3 2027; the later, dated programme clarification is used here. Main-building construction commencement is not confirmed.

Reality Score

52PossibleStatus: Approved
How we score
Planning25/25
Grid connection0/25
Land and funding20/20
Delivery team0/15
Momentum7/15

A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.

Early stage: worth a watching brief.

Supplying this project? Pro tells you every Monday when it moves →

Key facts

Operator / developer
Kao Data
Location
Stockport, North West, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
Not stated
Floor area
25,900 m²
Permanent jobs
40

Power & grid

Published capacity
  • 40 MW — Published IT loadThe IT load the operator or planning documents state the facility will draw.
Share of UK tracked capacity
0.8% of published it load
Grid connection
Kao Data statement, 1 July 2026: on-site substation and power-cabling work ongoing; power anticipated in late 2027. Operator forecast only; network connection offer and exact energisation date not independently verified. https://kaodata.com/discover/news/response-to-youtube-video/
Power
Kao Data's written evidence to the House of Commons (IGR0029, 13 January 2025) states the Stockport data centre will provide 40 MW of IT capacity. Recorded as IT load. Earlier press releases and adviser material describe a "40MW data centre" without defining the figure; the council application papers state floor area only.
Backup fuel
HVO
On-site generation
Up to 20 standby generators running on 100% HVO fuel (committee report). Generator MW not stated.

Planning

Planning route
Local planning (TCPA)
Planning reference
DC/090411
Planning decision
Approved at Heatons and Reddish Area Committee
Decision date
4 March 2024
Land area
4.06 ha
Recorded objections
1
Recorded support
1

Benefits vs drawbacks

Benefits

  • 40+ permanent jobs once operational, and about the same number of indirect jobsSource
  • Replaces a vacant, dilapidated industrial site; fewer vehicle movements than the previous industrial useSource
  • Standby generators to run on 100% HVO rather than dieselSource

Drawbacks

  • Residents raised traffic, noise, pollution and road-safety concernsSource
  • Up to 20 standby generators on a site near homesSource

Timeline

  1. Approved at Stockport Council's Heatons and Reddish Area Committee (DC/090411).

    Source

Sources

Last verified

15 October 2026