Back to the tracker

Kao Data Kenwood Point, Stockport

Kao Data

Stockport, North WestApproved Verified

Demolition of an existing industrial and warehouse building and erection of a 25,900 sq m data centre at Kenwood Point, Stockport, with associated parking, servicing and access. Approved by Stockport Council's Heatons and Reddish Area Committee. Applicant recorded as KD 5 Limited. Kao Data describes the scheme as a 40 MW data centre without stating whether that is IT load or grid capacity, so the figure is shown but excluded from totals. Programme update checked 8 October 2026: Kao Data's dated statement of 1 July 2026 says demolition is complete and the site has been prepared; substation and power-cabling works were ongoing. Main data-centre buildings are expected to be constructed in 2027, with power anticipated in late 2027 and operation in 2028. These are operator targets, not confirmed completion dates. The older location page still gives Q3 2027; the later, dated programme clarification is used here. Main-building construction commencement is not confirmed.

Key facts

Operator / developer
Kao Data
Location
Stockport, North West, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
Not stated
Floor area
25,900 m²
Permanent jobs
40

Power & grid

Published capacity
  • 40 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
Grid connection
Kao Data statement, 1 July 2026: on-site substation and power-cabling work ongoing; power anticipated in late 2027. Operator forecast only; network connection offer and exact energisation date not independently verified. https://kaodata.com/discover/news/response-to-youtube-video/
Power
The council application papers state floor area only and contain no power figure. The operator and its adviser describe a "40MW data centre" in press releases issued at acquisition and at approval, but none of them states whether that is IT load, grid connection capacity or total electrical demand, so it is not recorded as capacity and is excluded from every total.
Backup fuel
HVO
On-site generation
Up to 20 standby generators running on 100% HVO fuel (committee report). Generator MW not stated.

Planning

Planning route
Local planning (TCPA)
Planning reference
DC/090411
Planning decision
Approved at Heatons and Reddish Area Committee
Decision date
4 March 2024
Land area
4.06 ha
Recorded objections
1
Recorded support
1

Benefits vs drawbacks

Benefits

  • 40+ permanent jobs once operational, and about the same number of indirect jobsSource
  • Replaces a vacant, dilapidated industrial site; fewer vehicle movements than the previous industrial useSource
  • Standby generators to run on 100% HVO rather than dieselSource

Drawbacks

  • Residents raised traffic, noise, pollution and road-safety concernsSource
  • Up to 20 standby generators on a site near homesSource

Timeline

  1. Approved at Stockport Council's Heatons and Reddish Area Committee (DC/090411).

    Source

Reality Score

60Likely
How we score
Planning25/25
Grid connection0/25
Land and funding20/20
Delivery team15/15
Momentum0/15

Sources

Last verified

27 September 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.