Teesworks data centre campus (former Redcar Sinter Plant), Redcar

Redcar, North EastApproved

A data centre campus of up to 462,419 sqm on the former Redcar Sinter Plant at Teesworks, the former Redcar steelworks. Redcar and Cleveland Council granted reserved matters (R/2025/0382/ESM) on 1 August 2025 under the site's 2022 outline permission, despite bp's objection that it clashed with the H2Teesside hydrogen plant. No end user has been confirmed: Google was reported in talks in September 2025, and Private Eye reported in June 2026 that Anthropic had agreed in principle to buy 222 acres (unsigned, not confirmed by Anthropic). In late October 2026 National Grid agreed to buy 73.3 acres at Dorman Point for a 400 kV substation of about 1.44 GW, due by the end of 2029, to power a data centre on the site. Council papers in April 2026 recorded no development on site.

Reality Score

Not yet scored

Not buying yet. These projects in North East score Building or Likely:

Get the list of projects buying now →

Key facts

Operator / developer
South Tees Group / Teesworks Ltd
Location
Redcar, North East, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
High — AI/compute led
Floor area
462,419 m²

Power & grid

Grid connection
National Grid Electricity Transmission agreed in late Oct 2026 to buy 73.3 acres at Dorman Point, Teesworks, for the Tees Dock (Teesside Node A) 400 kV substation, initially about 1.44 GW (1,440 MVA) and due by end 2029, feeding a private-wire network to a new data centre plus BESS. Balfour Beatty reported as substation contractor. Substation itself still needs planning (outline application planned autumn 2026).

Planning

Planning route
Local planning (TCPA)
Planning reference
R/2025/0382/ESM
Planning decision
Reserved matters (appearance, landscaping, layout, access and scale) granted 1 August 2025 under outline permission R/2020/0821/ESM, despite an objection from bp linked to its H2Teesside project.
Decision date
1 August 2025
Land area
89.8 ha

Benefits vs drawbacks

Drawbacks

  • bp objected that the data centre was incompatible with its H2Teesside hydrogen project; the two schemes were assessed as unable to share the siteSource

Timeline

  1. Redcar and Cleveland Council grants reserved matters R/2025/0382/ESM for the data centre campus

    Source
  2. National Grid agrees to buy 73.3 acres at Dorman Point for a ~1.44 GW 400 kV substation to serve the data centre

    Source

Sources

Last verified

6 November 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.