Outline scheme by Humber Tech Park Ltd, a Greystoke Land company, for three AI-training data centre buildings, an on-site substation and a horticultural glasshouse using waste heat, on about 76 ha south of the A160 near South Killingholme. North Lincolnshire Council's planning committee approved outline application PA/2024/584 on 31 July 2024. Reported cost £2.2bn to £3bn and about 370 to 400 jobs. No end user named. Reserved matters still needed. Linked to the Northern Lincolnshire AI Growth Zone bid alongside Greystoke's Elsham Tech Park.
Reality Score
Not yet scored
Not buying yet. These projects in Yorkshire and the Humber score Building or Likely:
Get the list of projects buying now →Key facts
- Operator / developer
- Humber Tech Park Ltd (Greystoke Land)
- Location
- Land south of the A160, South Killingholme, South Killingholme, Yorkshire and the Humber, United Kingdom
- Status
- Approved
- Facility type
- Data centre
- AI relevance
- High — AI/compute led
- Stated investment
- £3,000,000,000
- Permanent jobs
- 370
Power & grid
- Published capacity
- 386 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
- Power
- 386 MW reported (DCD). New on-site electricity substation proposed; developer cites the South Humber Bank's North Sea gas and offshore wind supply.
Planning
- Council
- North Lincolnshire Council
- Planning route
- Local planning (TCPA)
- Planning reference
- PA/2024/584
- Planning decision
- Outline permission backed by North Lincolnshire Council planning committee on 31 July 2024.
- Land area
- 75.8 ha
Benefits vs drawbacks
Timeline
North Lincolnshire Council planning committee approves outline application PA/2024/584
Source
Sources
- Green light given to develop one of Europe's largest data centres
Secondary source · North Lincolnshire Council (primary) · 2024-08
- Decision made on £2.2bn data centre near South Killingholme
Secondary source · Grimsby Telegraph (secondary) · 2024-07-31
- Green light for 386MW data center campus in Lincolnshire, UK
Secondary source · DatacenterDynamics (secondary) · 2024-08
- £3bn Humber Tech Park clears planning (cites PA/2024/584)
Secondary source · Place North / Place Yorkshire (secondary)
Last verified
6 November 2026
Entering the UK data-centre market?
Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.