Skelton Grange, Leeds

Microsoft

Leeds, Yorkshire and the HumberApproved

A hybrid scheme for data centre buildings on the former Skelton Grange power station site at Stourton, Leeds, brought forward by Harworth Group with Microsoft. Leeds City Council's planning committee resolved to grant permission in April 2026, but no decision notice has been issued, so the scheme is not yet consented.

Skelton Grange planning status

Latest milestone
On 23 April 2026 Leeds City Council's Plans Panel resolved to grant permission for application 25/06139/FU, delegating the decision to the Chief Planning Officer subject to a section 106 agreement and conditions.Harworth Group plc (regulatory announcement)
Current position
When checked on 21 November 2026, the council's planning register still listed the application as current with no decision issued, so the scheme does not yet have planning permission.Leeds City Council planning register
Next expected decision
The next step is the formal decision notice, which follows completion of the section 106 agreement. No date for it has been published, so the timing is unknown.

Summary checked against this record on 21 November 2026. If anything differs, the detailed record and sources below take precedence. See the UK data centre map.

Reality Score

61LikelyStatus: Approved
How we score
Planning18/25
Grid connection0/25
Land and funding20/20
Delivery team8/15
Momentum15/15

A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.

Good evidence on several factors. Check for a named design or delivery team before planning an approach.

Supplying this project? Pro tells you every Monday when it moves →

Key facts

Operator / developer
Microsoft
Location
Leeds, Yorkshire and the Humber, United Kingdom
Status
Approved
Facility type
Data centre
AI relevance
Not stated

Power & grid

Power
No MW, MVA or IT-load figure appears in the council reporting, the Harworth market announcement or any other source retrieved. None is recorded.

Planning

Planning route
Local planning (TCPA)
Planning reference
25/06139/FU
Planning decision
Resolution to grant, Leeds City Council planning committee, April 2026; decision notice not yet issued
Land area
26.3 ha
Recorded objections
993

Benefits vs drawbacks

Benefits

  • About £4bn of inward investment on completion (Harworth estimate)Source
  • Reuses the former Skelton Grange power station siteSource
  • Microsoft says it will be air cooled more than 95% of the time; conditions require rainwater harvesting for much of its operational waterSource

Drawbacks

  • 993 formal objections; a petition against it has passed 44,000 signatures (Sep 2026)Source
  • Residents cite water and power use, noise, light and air pollution, and waste heatSource
  • No power, water or jobs figures publishedSource

Timeline

  1. Leeds City Council Plans Panel resolved to grant permission for the Microsoft data centre, delegated to the Chief Planning Officer subject to a S106 agreement and conditions.

    Source
  2. A 38 Degrees petition opposing the scheme passed 39,000 signatures; 993 formal objections reported.

    Source
  3. Petition against the scheme reported at more than 44,000 signatures, after about 250 people joined a Millennium Square protest organised by No Leeds Data Centre. West Yorkshire Mayor Tracy Brabin backed the scheme on economic grounds; Green group leader Cllr Penny Stables warned it would mean burning more gas.