Spodegreen Data Centre, Little Bollington
Renewable energy firm Innova proposes a data centre campus on about 60ha (148 acres) of Tatton Estate farmland near Little Bollington, Cheshire, beside the M56. The plans include data halls, offices, a training facility, a district heat network and a solar farm. The site is in the green belt. The scheme is at public consultation only: no planning application has been made, and one is expected to go to Cheshire East Council in late 2026 or early 2027. No power capacity has been published, and no operator or tenant is named. How to find the council record: For the Spode Green proposal, Cheshire East Council lists the site as land south of Lymm Road, Little Bollington. Open Innova’s Local Plan representation 6647 in the sources below. It identifies the land as Call for Sites reference 396. A formal planning application would have a separate reference.
Reality Score
A Reality Score assesses the public evidence behind a project. It is not its construction status, a probability of being built or a guarantee of procurement.
Public evidence for this project is limited so far. Projects in the UK with a higher score (Strong evidence or Likely):
- Pure DC LON01 B2, Brent Cross · Strong evidence · Under construction
- Era4 AI data centre, Erin Landfill, Chesterfield · Strong evidence · Operational
- GreenScale Derry Campus (formerly Atlantic Hub), Foyle Port · Strong evidence · Approved
Key facts
- Operator / developer
- Innova
- Location
- Land south of Lymm Road (A56), north of the M56 and west of the A556, near Little Bollington (Tatton Estate), Little Bollington, North West, United Kingdom
- Status
- Proposed
- Facility type
- Data centre
- AI relevance
- Not stated
Power & grid
- Grid position
- Grid connection application status not published
- Power
- No MW, MVA or IT-load figure has been published. The developer says the campus would be grid connected, with on-site substations and backup generation.
- On-site generation
- A solar farm (west of Coe Lane) plus rooftop and car-park solar panels are proposed.
- Cooling
- Hybrid air and closed-loop water cooling, which the developer says would minimise water use.
- Heat reuse
- A district heat network and energy centre are proposed.
Planning
- Council
- Cheshire East Council
- Planning route
- Local planning (TCPA)
- Green belt
- Yes
- Land area
- 60 ha
Benefits vs drawbacks
Benefits
Developer proposes apprenticeship and training funding, a "Living Lab" teaching space and EV charging; it projects about £20m in additional business rates for Cheshire East (basis not published).
Timeline
Sources
- Concern over 'monster' data center planned for Cheshire, UK
Secondary source · DCD (secondary) · 2026-10-02
- Rural Cheshire data centre put forward
Secondary source · Place North West (secondary) · 2026-09-30
- Spodegreen data centre: 60ha plan by M56, drop-in 30 Sept
Secondary source · Macclesfield Times (secondary) · 2026-09-27
- Spodegreen Data Centre project site
Secondary source · Innova (developer, primary) · 2026-11-05
- How to find the council record: Innova representation 6647, Call for Sites reference 396
Primary record · Cheshire East Council (Local Plan consultation register) · 2026-09-01
Last verified
5 November 2026