Telehouse Inventory Estate data centre, East India Dock
Telehouse (KDDI)
Telehouse, owned by KDDI, completed its purchase of the Inventory Estate at East India Dock for more than £220m in late October 2026, next to its London Docklands campus. The site carries outline consent, won at appeal in 2023, for a 35,000 sqm data centre. Telehouse says 65MVA of power is secured. No construction date has been announced.
Reality Score
Early stage: worth a watching brief.
Supplying this project? See the Market Entry Sprint →Key facts
- Operator / developer
- Telehouse (KDDI)
- Location
- London (Blackwall), London, United Kingdom
- Status
- Approved
- Facility type
- Data centre
- AI relevance
- stated
- Floor area
- 35,000 m²
- Stated investment
- £220,000,000
Power & grid
- Published capacity
- 65 MW — Published grid-connection capacityThe connection capacity secured or applied for, which is not the same as demand.
- Share of UK tracked capacity
- 14.9% of published grid-connection capacity
Planning
- Planning route
- Local planning (TCPA)
- Planning decision
- Outline consent for a 35,000 sqm data centre granted at appeal Oct 2023, after Tower Hamlets refused the wider scheme in Oct 2022
- Appeal status
- Appeal allowed
Sources
- Telehouse closes acquisition of Docklands office campus, plans 65MW data center
Secondary source · DCD (secondary) · 2026-10-29
- Inspector overturns councillors' rejection of mixed-use east London scheme
Secondary source · Housing Today (secondary)
- London docks data centre go-ahead after planning victory
Secondary source · Real Asset Insight (secondary)
- KDDI secures 65MVA for London data centre site
Secondary source · The Tech Capital (secondary) · 2026-10-30
Last verified
5 November 2026
Entering the UK data-centre market?