Hamilton, ScotlandProposedData centreCapacity not published Verified — 1 source on file
A data centre campus with ancillary offices, back-up generators, fuel storage, a battery energy storage system and an electricity substation is proposed at Haspielaw Farm, Hamilton. South Lanarkshire Council issued an environmental screening opinion on 25 June 2025 confirming an environmental impact assessment is required. This is a pre-application procedural step: no planning application for the campus has been determined.
Project detail
- Operator / developer
- Not published
- Location
- Hamilton, Scotland, United Kingdom
- Status
- Proposed
- AI relevance
- Not stated
- Announced
- Not published
- Target live date
- Not published
- Published capacity
- Not published. No capacity figure means none has been published — it does not mean zero.
- Floor area
- Not published
- Stated investment
- Not published
- Power
- Not published
- Grid connection
- Not published
- Cooling
- Not published
- Water
- Not published
- Planning authority
- South Lanarkshire Council
- Planning reference
- P/25/0490
- Planning decision
- EIA screening opinion issued: environmental impact assessment required
- Decision date
- 2025-06-25
- Construction start
- Not published
- Expected completion
- Not published
- Operational since
- Not published
- Confidence
- Medium confidence
- Last verified
- 2026-08-12
Sources
- Planning application P/25/0490 - EIA screening opinion request, proposed data centre campus, Haspielaw Farm, Hamilton
Primary record · South Lanarkshire Council · 2025-06-25 · accessed 2026-08-12
Entry last updated 12/08/2026. Spotted something wrong? Tell us.
Scotland in context
See every tracked project in Scotland, the capacity that has been disclosed there and how it connects to wider UK demand.