North East England AI Growth Zone (Cobalt Park & Blyth)
Blackstone (via QTS) at Blyth; Nscale at Cobalt Park (Stargate UK paused April 2026)
UK's second AI Growth Zone, announced in September 2025 alongside the UK-US Tech Prosperity Deal, anchored at Cobalt Park (North Tyneside) and Blyth (Northumberland). Stargate UK, a joint venture between OpenAI, Nvidia and British firm Nscale, was announced to deploy sovereign AI compute at Cobalt Park, starting with 8,000 GPUs and scaling to 31,000. OpenAI paused Stargate UK on 9 April 2026, citing energy costs and regulation, and says it could proceed if conditions allow. Blackstone has committed GBP 10bn to the Blyth site via its QTS subsidiary, with the AI Growth Zone designation creating headroom for a further GBP 20bn from other partners.
Reality Score
Not yet scored
This project has no published Reality Score yet. Projects in North East with a higher score (Strong evidence or Likely):
- Cambois data centre campus · Likely · Under construction
Key facts
- Operator / developer
- Blackstone (via QTS) at Blyth; Nscale at Cobalt Park (Stargate UK paused April 2026)
- Location
- Wallsend & Blyth, North East, United Kingdom
- Status
- Approved
- Facility type
- AI growth zone
- AI relevance
- High — AI/compute led
- Announced
- 16 September 2025
- Stated investment
- £30,000,000,000
- Jobs
- More than 5,000 (government estimate)
- Stargate UK
- Announced Sep 2025 (OpenAI/Nvidia/Nscale at Cobalt Park, up to 8,000 GPUs scaling to ~31,000); paused by OpenAI on 9 Apr 2026
- Blyth investment
- GBP 10bn committed by Blackstone via QTS, with GBP 20bn further potential
- Wider package
- £31 billion of US tech investment announced across UK AI infrastructure
Power & grid
- Published capacity
- 1,100 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
- Power
- Combined energy capacity target of 1.1GW within six years across the zone. Cobalt Park hosts the existing Stellium colocation campus (currently up to 80MW, scaling toward 180MW); Blyth hosts a new Blackstone/QTS hyperscale build.
Benefits vs drawbacks
Benefits
£5m of government funding for local AI adoption and skills; North East Combined Authority prospectus covers skills, adoption, innovation and infrastructure.
Timeline
Sources
- US-UK pact will boost advances in drug discovery, create tens of thousands of jobs and transform lives
Secondary source · DSIT / Prime Minister's Office (GOV.UK) · 16 September 2025
- US-UK tech deal agreed as AI Growth Zone announced for north east of England
Secondary source · DatacenterDynamics · 18 September 2025
- North East England set for billions in investment and thousands of jobs through new AI Growth Zone
Secondary source · UK Government / North East Combined Authority · 18 September 2025
- OpenAI puts Stargate UK on ice over energy cost, regulations
Secondary source · The Register · 9 April 2026
- AI Growth Zones yet to accelerate planning activity, FOI data suggests
Secondary source · Data Centre Review · 20 August 2026
- Strategic Planning Committee report, application 24/04112/OUTES, Land at former power station site, Cambois
Secondary source · Northumberland County Council · 2025-03-04
- AI Growth Zone
Secondary source · North East Combined Authority
Last verified
8 November 2026