Ark Data Centres' modular campus at Longcross Park, the first commercial development in Longcross Garden Village (Runnymede), part of the Enterprise M3 Enterprise Zone. AI cloud firm Nebius signed in June 2025 (initial 4,000 Nvidia Blackwell Ultra GPUs, live November 2025) and by June 2026 had taken the whole LP01 building. In June 2026 Ark announced an £807m expansion: vertical extensions to existing buildings, infrastructure upgrades and a new 36 MW building, LP02.

Reality Score

Not yet scored

Not buying yet. These projects in South East score Building or Likely:

Get the list of projects buying now →

Key facts

Operator / developer
Ark Data Centres
Location
Longcross Park, Chobham Lane, Longcross, South East, United Kingdom
Status
Operational
Facility type
Data centre
AI relevance
High — AI/compute led
Stated investment
£807,000,000

Power & grid

Power
Expansion announced June 2026 includes vertical extensions to the existing buildings, infrastructure upgrades and a separate new 36 MW building (LP02). Campus total not confirmed by Ark (an industry database gives 54 MW across two buildings).

Planning

Planning route
Local planning (TCPA)

Timeline

  1. Ark announces new building (LP02, 36 MW) and extensions at Longcross; £807m investment

    Source

Sources

Last verified

6 November 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.