Google's first UK data centre, on a 33-acre site at Waltham Cross, Hertfordshire, which Google bought in October 2020. Construction of the $1bn (about £790m) facility was announced on 18 January 2024. It was opened by the Chancellor on 16 September 2025 as part of Google's two-year £5bn UK investment, to support Google Cloud, Workspace, Search and Maps, including AI services. Google gives no capacity figure. The site is Maxwells Farm West (Theobalds Business Park), Cheshunt, in the Borough of Broxbourne; the planning applicant for the data centre was Global Infrastructure UK Ltd.

Key facts

Operator / developer
Google
Location
Waltham Cross, East of England, United Kingdom
Status
Operational
Facility type
Data centre
AI relevance
Not stated
Announced
18 January 2024

Planning

Planning route
Local planning (TCPA)
Planning reference
07/18/1181/O (outline); 07/23/0361/RM (data centre reserved matters)
Planning decision
Committee resolved to grant reserved matters on 12 Sep 2023. Decision-notice dates not confirmed.
Land area
13.4 ha

Timeline

  1. Broxbourne Planning and Regulatory Committee resolved to grant reserved matters 07/23/0361/RM for the data centre (Phase 3, Maxwells Farm West) under outline 07/18/1181/O, subject to drainage, noise and air quality matters and a unilateral obligation.

    Source
  2. Environment Agency advertised bespoke permit application EPR/ZP3128SD/A001 by Global Infrastructure UK Limited (combustion plant over 50MWth) for the data centre at Maxwells Farm West, Cheshunt EN8 8XH.

    Source

Sources

Last verified

3 October 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.