Lanarkshire AI Growth Zone

DataVita, in partnership with CoreWeave

Airdrie, ScotlandApproved Verified

Scotland's AI Growth Zone, delivered by data centre company DataVita around its Airdrie site in partnership with AI cloud firm CoreWeave. Government states £8.2 billion of private investment is committed, supporting more than 3,400 jobs and including a renewables park alongside the data centres.

Reality Score

Not yet scored

This project has no published Reality Score yet. Projects in Scotland with a higher score (Strong evidence or Likely):

Request a sample report on higher-scoring projects →

Key facts

Operator / developer
DataVita, in partnership with CoreWeave
Location
Airdrie, Scotland, United Kingdom
Status
Approved
Facility type
AI growth zone
AI relevance
High — AI/compute led
Announced
29 January 2026
Stated investment
£8,200,000,000
Private investment committed
£8.2 billion
Jobs
More than 3,400, including around 800 high-paying AI roles
Community fund
Up to £543 million over 15 years (GOV.UK)
On-site energy
Renewables park planned alongside data centres
Aug 2026 financing
£300m debt facility (GOV.UK, 18 Aug 2026) funding expansion of the existing DataVita DV1 datacentre and construction of a new DV3 building at Chapelhall -- see the DataVita DV3 record
Dell Technologies
Dell Technologies established a Scottish base at Mercury House on the AI Innovation Park, announced alongside the £300m financing (GOV.UK, 18 Aug 2026)

Power & grid

Published capacity
  • 500 MW — Reported capacity, definition not publishedA megawatt figure was reported but the source does not define what it measures, so it is excluded from every total.
Power
DataVita states a total capacity of 500 MW for its Lanarkshire campus, and separately more than 1 GW of private-wire renewable generation, which is generation rather than demand and is not a data-centre load figure. The 500 MW is an operator claim for an area-wide programme, not a consented facility figure, and does not appear in the UK Government designation statement of 29 January 2026. It is excluded from every total.
On-site generation
Originally presented with 500MW+ of on-site renewable generation (government, Jan 2026) and DataVita's pledge of more than 1GW of private-wire wind, solar and battery capacity. On 7 Nov 2026 DataVita told the Guardian its data centres are "being designed to be grid served", with renewable power bought through a power purchase agreement; a wind and solar park elsewhere in North Lanarkshire "could connect in the future".
Heat reuse
Excess heat from cooling planned for University Hospital Monklands (government).

Benefits vs drawbacks

Benefits

  • More than 3,400 jobs, including about 800 high-paying AI roles (government estimate)Source
  • Community fund of up to £543m over 15 yearsSource
  • Anchor tenant signed (CoreWeave) and construction financed (£300m, Aug 2026)Source
  • Planned heat reuse for University Hospital MonklandsSource

Drawbacks

  • 500MW campus capacity is an operator claim, not a consented figureSource
  • Heavy reliance on one tenant (CoreWeave)Source
  • Private-wire renewables pledge dropped: DataVita now says the site will be fully grid served, buying renewable power through a PPASource

Community fund of up to £543m over 15 years (skills, apprenticeships, coding clubs, charities and foodbanks); £1m a year from HFD Group for local charities; 50 apprenticeships; £5m government funding.

Timeline

  1. Lanarkshire named Scotland's AI Growth Zone, led by DataVita with CoreWeave.

    Source
  2. £300m debt facility and Dell's Scottish base announced for the zone.

    Source
  3. DataVita told the Guardian its Chapelhall data centres will be "fully grid served", with renewables bought through a power purchase agreement, replacing the earlier pledge of more than 1GW of private-wire renewables.

    Source

Sources

Last verified

11 November 2026

Email me when this changes