Crawley, South EastOperational Verified

Operational campus at Manor Royal. Verified through the Environment Agency permit for standby generation; the underlying planning consent was not retrieved.

Key facts

Operator / developer
Digital Realty
Location
Manor Royal, Crawley, RH10 9BD, South East, United Kingdom
Status
Operational
Facility type
Data centre
AI relevance
Not stated

Power & grid

Backup fuel
Diesel
On-site generation
17 standby generators on gas oil, about 72.6 MWth in total; testing under 50 hours per generator per year; 500-hour installation emergency cap (EA decision document, June 2025).

Planning

Planning reference
EPR/EP3022ST/A001 (environmental permit)
Planning decision
Environmental permit issued
Decision date
9 June 2025

Benefits vs drawbacks

Drawbacks

  • 17 gas oil standby generators, about 72.6 MWthSource

Timeline

  1. Environment Agency issued an environmental permit (EPR/EP3022ST/A001).

    Source

Sources

Last verified

12 August 2026

Entering the UK data-centre market?

Our 3-week Market Entry Sprint shows which projects to chase, who buys the packages, and what to do in the next 90 days. Built on the same sourced data as this tracker.

Email me when this changes

Get an email when we update this project's published record.