UK Data Centres: Gas Power Proposals Branded 'Insane' Amidst Energy Concerns

25 September 2026 8 min readSource: bbc.co.uk
Why are data centres in East of England being branded 'insane'?

Executive summary

Two proposed hyperscale data centres in Bedfordshire and Buckinghamshire are facing criticism for plans to include on-site gas power stations to provide energy resilience. Councillors and environmental groups have labelled these proposals 'insane' due to their potential climate impact, while developers maintain their energy strategies are still in development.

Reporting based on bbc.co.uk

Why it matters

This report highlights a critical tension in the UK's pursuit of AI infrastructure: the substantial energy demands of hyperscale data centres clashing with net-zero targets. The reliance on on-site gas generation for resilience raises significant questions about the carbon footprint of future AI development and the planning process for nationally significant infrastructure.

Sector impact

Analysis by AI Energy Intelligence UK

UK electricity demand

Data centres currently consume approximately 2.5% of the UK's electricity. The proposed Quest Park facility alone would require a 1GW power load, while SDC's site would need 300MW. To put this in perspective, 1GW of electricity could power three million average British homes, indicating a substantial increase in demand from these new facilities.

UK energy security

Developers propose on-site gas power for 'resilience' to prevent heavy demand on the National Grid, with plans to connect to the grid once it can meet their specific demands. This indicates a perceived inability of the current grid infrastructure to immediately accommodate such large-scale electricity requirements without additional, dedicated generation.

Businesses

The government views data centres as 'critical infrastructure' vital for national security and personal data protection, essential to the economy and services. Developers Quest Park and SDC Capital Partners anticipate their projects will create over 1,000 and 400 jobs respectively, alongside significant investment.

Consumers

While not directly detailed for consumers, the article notes benefits of data centres such as 'faster internet' and 'cloud-based working', implying that consumer access to such services relies on this infrastructure. However, local communities express feeling 'blindsided' by the planning process, suggesting a disconnect between national strategic needs and local concerns.

Key statistics

2.5% of the UK's electricity
Current UK electricity consumption by data centres
30GW
UK's average daily energy demand
25GW and 33GW
UK's average daily electricity generation range
1GW
Quest Park proposed power load
300MW
SDC proposed power load
three million average British homes
Equivalent homes powered by 1GW
4.5m tonnes per year
Estimated combined greenhouse gas emissions of both plants (Foxglove, worst case)
1.3m tonnes
Luton Airport's emissions (2025)

Figures as reported by bbc.co.uk. See original source for context.

Quotations

"I'm not AI [artificial intelligence] averse, but saying we can't get enough electricity so we need a gas power station is a really terrible idea."

— Susan Clinch, a Central Bedfordshire councillor

"The International Energy Agency notes that the carbon savings enabled by AI could be three to four times larger than the emissions created by the data centres themselves"

— a government spokesperson

"They're really critical to our economy and they're really critical to the services that we all rely on"

— Blake Stephenson, Conservative MP for Mid Bedfordshire

"I'm flabbergasted, it's insane"

— Buckinghamshire independent councillor Ed Gemmell

"We are not against data centres as long as they come with their own independent energy source – but we assumed that would be renewables."

— Ed Gemmell

"Ideally they should be built near the coast to incorporate tidal power, which is totally reliable"

— Ed Gemmell

"The biggest concern from local people is the way these NSIP applications happen. The community feels blindsided."

— Rebecca Hare, independent councillor for Houghton Conquest on Central Bedfordshire Council

"There are obviously benefits [to data centres]: faster internet, cloud-based working, working from home, but we're bearing the brunt of a lot of national infrastructure in this area."

— Rebecca Hare

"It feels like national strategy doesn't make sense – with these gas works required to fuel it, when we're working towards net zero."

— Rebecca Hare

"Not building new data centres would simply send investment and good jobs abroad, while leaving Britain dependent on other countries for processing sensitive health and defence data."

— A government spokesperson

"This does not mean a blank cheque for big tech, or that every data centre should be approved. Developers should prioritise clean power, use water responsibly, create British jobs and supply chains, and provide investment to the communities in which they are built."

— A government spokesperson

Long-term implications

The shift in planning regulations, allowing data centres to be approved by the government as 'nationally significant infrastructure projects', suggests a streamlined path for their development. However, the controversy over on-site gas power and the significant carbon emissions estimations (e.g., 4.5m tonnes per year for both plants) pose a challenge to the UK's long-term net-zero commitments and may necessitate a more rigorous environmental framework for future AI infrastructure.

Artificial Intelligence (AI)Hyperscale Data CentresGas Power StationsRenewable EnergySolar ElectricityWind PowerTidal Power

Frequently asked questions

Why are data centres in the East of England being criticised?

Two proposed hyperscale data centres in Bedfordshire and Buckinghamshire are facing criticism because their plans include on-site gas power stations, which councillors and environmental groups consider detrimental to climate goals.

How much electricity would these data centres require?

The Quest Park data centre would have a power load of 1GW, and the SDC site would require 300MW. For context, 1GW could power three million average British homes.

What is the climate impact concern?

Foxglove, a campaign group, estimates that if both proposed gas plants operate at full capacity, their combined greenhouse gas emissions could be as high as 4.5m tonnes per year.

How are these data centres getting planning permission?

Data centres can now be designated as 'nationally significant infrastructure projects' (NSIP), allowing them to apply directly to the Planning Inspectorate for permission, bypassing local councils.

What is the government's stance on data centres?

The government has designated data centres as 'critical infrastructure' for national security and data protection, stating that not building them would send investment and jobs abroad. However, they expect developers to prioritise clean power and responsible practices.

Original source

This story summarises reporting from bbc.co.uk. Read the original for full context.

Read on bbc.co.uk
Share
Reports & Research

Recommended reports

Independent UK research that expands on the themes in this story.

Browse all reports

Get the UK AI Energy briefing

Analysis on AI, electricity and the UK grid, straight to your inbox.

Weekly AI business briefing
Practical AI insights for UK businesses, every Friday.

We use your email to send your report and (if you've opted in) the weekly briefing. Unsubscribe any time. See our privacy policy.

Evidence base

Evidence behind this story

Our reporting sits on top of the UK AI Energy Index and Data Centre Tracker — a sourced, dated record of AI and data-centre electricity demand, data-centre development and grid pressure.