Back to Analysis & Research

Why Data Centre Megawatt Announcements Can Mislead

Megawatts measure power, not electricity used. A practical guide to IT load, connection capacity, PUE and the five questions to ask about any data centre capacity announcement.

Peter Flynn18 September 20265 min readAI Electricity Demand
Why Data Centre Megawatt Announcements Can Mislead

Key findings

  • Megawatts measure power at an instant; MWh, GWh and TWh measure electricity used over time. One cannot be converted to the other without a load factor.
  • IT load, whole-facility power and grid connection capacity are three different figures, and headlines rarely say which is quoted.
  • Announced, approved, connected and operational capacity are separate states that rarely coincide.
  • PUE, defined in ISO/IEC 30134-2, is a ratio of total facility energy to IT energy; it says nothing about absolute consumption or carbon.
  • An illustrative 100 MW IT load at a 70% load factor and PUE of 1.2 gives about 736 GWh a year — using assumed, not measured, inputs.
  • No official UK dataset separates AI electricity consumption from other data centre consumption.
Share

Executive summary

A data centre announced at "500 MW" tells you far less than it appears to. Megawatts measure power, not electricity used; the figure quoted may describe computing equipment, the whole building or a grid connection; and it usually refers to an eventual build-out rather than anything operating now. This guide sets out the distinctions, works through a clearly labelled illustrative calculation, and ends with five questions worth asking about any capacity announcement.

Why this matters to the UK

British debate about AI and electricity runs on announced megawatts. Those figures feed into arguments about bills, grid capacity and whether the country can supply what is being planned. When power and energy are used interchangeably, or a connection capacity is reported as consumption, the resulting numbers can be out by a factor of several — usually upwards.

Power and energy are not the same measure

Megawatts (MW) measure power — a rate

A megawatt is one million watts: the rate at which electricity is being used at an instant. It is the size of the tap, not the volume of water. A facility rated at 100 MW has a maximum; it does not run at that maximum continuously.

Megawatt-hours (MWh), gigawatt-hours (GWh) and terawatt-hours (TWh) measure energy

Energy is power multiplied by time. One megawatt sustained for one hour is one megawatt-hour. A thousand MWh is a GWh; a million MWh is a TWh. Electricity bills, national statistics and carbon accounting are all in energy units. A megawatt figure cannot be converted into an energy figure without knowing how heavily, and for how long, the equipment runs.

Which megawatts are being quoted?

TermWhat it measuresCommon misreading
IT load (IT capacity)Maximum power available to computing equipment — servers, storage, networkTreated as whole-facility demand, which excludes cooling and power losses
Whole-facility powerIT load plus cooling, power conversion and building servicesAssumed equal to IT load
Grid connection capacityMaximum import the network agreement permits at that siteReported as electricity the site consumes
Initial operating capacityThe first phase actually energisedConflated with the full campus figure
Ultimate build-outCapacity if every phase is delivered, often over a decadeReported as current or near-term capacity
PUERatio of total facility energy to IT equipment energyRead as a measure of how much electricity a site uses, or how "green" it is
Annual consumption (MWh/GWh)Electricity actually used over a periodAssumed to follow directly from a MW headline

Announced, approved, connected, operational

These four are separate states and rarely coincide. An announced capacity is a developer's statement of intent. An approved capacity has planning consent, which says nothing about power. A connected capacity has a grid agreement — a right to import, not a load. Only an operational facility draws electricity, and it draws what its workload requires, not its rating. Our analysis of the UK data centre pipeline shows how few tracked projects disclose any defined figure at all.

What PUE does and does not establish

Power usage effectiveness, defined in ISO/IEC 30134-2, is the ratio of total data centre energy to the energy delivered to IT equipment. A PUE of 1.2 means 1.2 units of electricity enter the facility for every unit reaching the computing equipment; the balance is mostly cooling and electrical losses.

PUE is a ratio, so it says nothing about absolute consumption: a very large facility with an excellent PUE uses far more electricity than a small inefficient one. It also says nothing about carbon intensity, water use, or how useful the computing work was. An annualised, measured PUE is a meaningful operating metric; a design PUE quoted in a planning application is a target.

A worked example — illustrative assumptions only

The following calculation uses invented inputs to show the method. It is not a measurement, a forecast, or a description of any real project.

Assume a facility with 100 MW of maximum IT load, averaging 70% of that electrical load across a full year of 8,760 hours, with an annual PUE of 1.2.

StepCalculationResult
Average IT power100 MW × 0.7070 MW
Average whole-facility power70 MW × 1.284 MW
Annual whole-facility electricity84 MW × 8,760 hours735,840 MWh, or about 736 GWh

Three cautions. The 70% figure is an electrical load factor — the share of maximum IT power drawn on average — not GPU utilisation, which is a different quantity. The PUE of 1.2 is assumed, not measured. And the method breaks if the headline 100 MW is in fact a grid connection capacity or a whole-facility rating: applying an IT-load calculation to those would inflate the answer. You can vary these inputs yourself in our data centre electricity calculator.

Why data centre electricity is not all AI

Data centres have hosted email, video streaming, banking, retail and government systems for decades. AI training and inference are additions to that workload, often inside the same buildings. No official UK dataset separates AI electricity consumption from other data centre consumption, because metering is by site, not by workload. A facility marketed as AI-ready may run substantial conventional load; a conventional facility may run AI inference. Attributing a site's whole consumption to AI overstates AI's share by an unknown margin. We keep that distinction in the electricity demand section of the UK AI Energy Index.

Five questions to ask about any capacity announcement

  1. What is being measured? IT load, whole-facility power, or grid connection capacity?
  2. Which phase does it cover? The first building, or an ultimate build-out across the whole site?
  3. What is the delivery status? Announced, consented, connection agreed, under construction, or in service?
  4. What load is actually expected? Is there a stated utilisation or load factor, and a measured or designed PUE?
  5. Where does the figure come from? A planning document, a regulatory filing, a company statement — and on what date?

If the answer to any of these is unavailable, the honest treatment is to record the figure as unverified rather than convert it into a consumption estimate. That is how we handle it in the UK data centre tracker, and why many records show capacity as unknown.

Sources

The worked example uses hypothetical assumptions of 100 MW IT load, a 70% annual electrical load factor and a PUE of 1.2. It is not a measurement or a forecast.

Methodology

Definitions are taken from the published standard for PUE and from official UK energy statistics conventions. The worked example uses stated hypothetical inputs and elementary arithmetic; each step is shown so the assumptions can be replaced.

Limitations

The worked example is illustrative only and describes no real facility. Load factors and PUE vary widely by site and are rarely published in measured, annualised form. No UK source separates AI workload electricity from other data centre electricity, so the AI share of any site's consumption remains unquantified.

Sources

  1. ISO/IEC 30134-2 — Data centres key performance indicators, Part 2: Power usage effectiveness (PUE)ISO/IEC (accessed 2026-09-18)
  2. Energy consumption in the UKDepartment for Energy Security and Net Zero (accessed 2026-09-18)
  3. Proposed data centre connection reforms (consultation)Ofgem (accessed 2026-09-18)

Spotted an error? Request a correction.

Try the numbers yourself

Free interactive tools from AI Energy Intelligence UK — no signup required.

Share
#Megawatts#PUE#Capacity#Electricity demand#Explainer
Evidence base

Evidence behind this analysis

Our reporting sits on top of the UK AI Energy Index and Data Centre Tracker — a sourced, dated record of AI and data-centre electricity demand, data-centre development and grid pressure.