North East England AI Growth Zone (Cobalt Park & Blyth)
Wallsend & Blyth, North East Verified against published sources
UK's second AI Growth Zone, announced in September 2025 alongside the UK-US Tech Prosperity Deal, anchored at Cobalt Park (North Tyneside) and Blyth (Northumberland). Stargate UK -- a joint venture between OpenAI, Nvidia and British firm Nscale -- will deploy sovereign AI compute at Cobalt Park, starting with 8,000 GPUs scaling to 31,000. Blackstone has committed GBP 10bn to the Blyth site via its QTS subsidiary, with the AI Growth Zone designation creating headroom for a further GBP 20bn from other partners. In April 2026 OpenAI paused Stargate UK, citing energy costs and regulation; it says it will proceed when conditions allow.
Investment
- Stated investment
- £30bn
- Lead organisations
- Blackstone (via QTS) at Blyth; Stargate UK (OpenAI, Nvidia, Nscale) at Cobalt Park
- Announced
- 16 September 2025
- Target live
- Not published
Power and grid
- Published capacity
- 1,100 MW
- Power notes
- Combined energy capacity target of 1.1GW within six years across the zone. Cobalt Park hosts the existing Stellium colocation campus (currently up to 80MW, scaling toward 180MW); Blyth hosts a new Blackstone/QTS hyperscale build.
- Grid connection
- Not published
- Cooling and water
- Not published
Planning
- Planning authority
- Not published
- Planning reference
- Not published
- Current status
- Approved
- Floor area
- Not published
Evidence quality
- Confidence
- High confidence
- AI relevance
- High — AI/compute led
- Verified
- Yes
- Last updated
- 8 October 2026
AI use
- Tenant or end user
- Stargate UK (OpenAI, Nvidia, Nscale) at Cobalt Park, paused April 2026; QTS (Blackstone) at Blyth
- AI compute
- Stargate UK planned up to 8,000 Nvidia GPUs at first, scaling to about 31,000, at Nscale capacity in Cobalt Park. OpenAI paused it on 9 Apr 2026.
Benefits vs drawbacks
Benefits
Member projects
- Cambois data centre campus
Cambois · Under construction
- Cobalt Data Centre Campus (Stellium)
Wallsend · Operational
Timeline
Progress
Announced · 16 September 2025
Zone announced by government
US-UK pact will boost advances in drug discovery, create tens of thousands of jobs and transform livesdesignation · 18 September 2025
Designated AI Growth Zone; Stargate UK launch announced
North East England named UK's second AI Growth Zone, anchored at Cobalt Park and Blyth. OpenAI, Nvidia and Nscale announced Stargate UK sovereign compute platform at Cobalt Park.
US-UK tech deal agreed as AI Growth Zone announced for north east of England
Key facts as published
- Jobs
- More than 5,000 (government estimate)
- Stargate UK
- OpenAI/Nvidia/Nscale sovereign AI compute deployment at Cobalt Park, phase one up to 8,000 GPUs, scaling to ~31,000
- Blyth investment
- GBP 10bn committed by Blackstone via QTS, with GBP 20bn further potential
- Wider package
- £31 billion of US tech investment announced across UK AI infrastructure
Sources
- US-UK pact will boost advances in drug discovery, create tens of thousands of jobs and transform lives — DSIT / Prime Minister's Office (GOV.UK), 16 September 2025
- US-UK tech deal agreed as AI Growth Zone announced for north east of England — DatacenterDynamics, 18 September 2025
- North East England set for billions in investment and thousands of jobs through new AI Growth Zone — UK Government / North East Combined Authority, 18 September 2025
- OpenAI puts Stargate UK on ice over energy cost, regulations — The Register, 9 April 2026
- AI Growth Zones yet to accelerate planning activity, FOI data suggests — Data Centre Review, 20 August 2026
- Strategic Planning Committee report, application 24/04112/OUTES, Land at former power station site, Cambois — Northumberland County Council, 2025-03-04
- AI Growth Zone — North East Combined Authority
Where this connects
- Tracker entry for North East England AI Growth Zone (Cobalt Park & Blyth) — the same record inside the UK data-centre tracker.
- All tracked projects in North East
- UK AI Energy Index — the indicators we track for AI-driven electricity demand.